CONSTRUCTION MANAGEMENT AS ADVISOR CMA SERVICES EXPANSION & MODERNIZATION PROJECT, PHASE 1 AT THE SAN LUIS I LAND PORT OF ENTRY
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
11 actions since 2022-12-09. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-07 | PS0014 | Supplemental agreement (work within scope) | $295.4K | MODIFICATION TO COMPLETE THE ALTA SURVEY & MEASUREMENT & VERIFICATION SERVICES PER RFP #011. THIS MODIFICATION IS IN THE TOTAL AMOUNT OF $295,444.00. |
| 2026-06-11 | PA0013 | Administrative change | $0 | THE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO RECOGNIZE A SUCCESSOR IN INTEREST TO THIS ORDER RESULTING FROM A NOVATION AGREEMENT EXECUTED UNDER GSA MAS CONTRACT GS00F038CA AND IMPLEMENTED AT THE BPA LEVEL UNDER BPA 47PD0319A0005. |
| 2025-08-06 | PC0012 | Funding only | -$2.9K | THIS CONTRACT MODIFICATION IS ISSUED TO DEOBLIGATE THE REMAINING $2,874.00 OF UNSUED FUNDING PROVIDED TO COMPLETE THE NORTHEAST PARCEL TITLE REPORT IN IDENTIFIED IN PREVISOUS MODIFICATION PS004. |
| 2025-03-14 | PS0011 | Supplemental agreement (work within scope) | $454.5K | MODIFICATION REQUIRED AND IDENTIFIED IN THE SOW PER RFP 10. MODIFICATION IN THE TOTAL AMOUNT OF $454,476 AND ALSO DEFINITIZES PC0010 IN THE TOTAL AMOUNT OF $1,154,476.00. CONTRACT END DATE IS EXTENDED FROM 3/24/2028 UNTIL 10/23/2028. |
| 2025-01-17 | PC0010 | Supplemental agreement (work within scope) | $700.0K | THIS NTE MODIFICATION IS TO PROCEED WITH THE SOW REQUIRED BY RFP #0010 DATED 8/26/2024. THIS MODIFICATION IS IN THE NTE AMOUNT OF $700,000.00. NO CONTRACT TIME EXTENSION IS GRANTED. ALL OTHER TERMS AND CONDITIONS OF THIS CONTRACT REMAIN UNCHANGED. |
| 2024-01-11 | PS0009 | Supplemental agreement (work within scope) | $2.97M | MODIFICATION IS ISSUED FOR THE ADDITIONAL GSA OPTIONS INCORPORATED INTO THE PROJECT PER THE SOW INCLUDED IN RFP 005 IN SUPPORT OF THE EXPANSION & MODERNIZATION PROJECT AT THE SAN LUIS I LPOE. MODIFICATION IS IN THE TOTAL AMOUNT OF $2,973,209.00. |
| 2023-12-12 | PA0008 | Funding only | -$88.2K | FINALIZING COST TRANSFER FOR JACOBS CONTRACT AND DEOBLIGATE/DELETE TEMPORARY CLIN 0011. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2023-10-11 | PA0007 | Funding only | $88.2K | COST TRANSFER FROM BA11 TO BA24 FOR CMA LEC MARKET STUDY |
| 2023-07-06 | PS0006 | Change order definitized | $38.2K | MODIFICATION TO PERFORM MARKET RESEARCH FOR LEC MATERIALS PER RFP #004. TOTAL AMOUNT FOR THIS WORK IS $88,216.00. THE GSA ISSUED MODIFICATION PC0005 IN THE AMOUNT OF $50,000.00. THIS MODIFICATION IS IN THE AMOUNT OF $38,216.00 AND DEFINITIZES PC0005. |
| 2023-05-19 | PC0005 | Supplemental agreement (work within scope) | $50.0K | UNILATERAL NTE MODIFICATION TO COMPLETE THE LEC MATERIALS ALTERNATIVES MARKET RESEARCH STUDY & REPORT PER RFP#4. WORK IS IN SUPPORT OF THE EXPANSION & MODERNIZATION PROJECT AT THE SAN LUIS I LPOE. MODIFICATION IS IN THE NTE AMOUNT OF $50,000.00. |
| 2022-12-09 | PS0004 | Supplemental agreement (work within scope) | $4.6K | MODIFICATION TO COMPLETE THE NORTHEAST PARCEL TITLE REPORT IDENTIFIED IN THE ATTACHED SOW DATED NOVEMBER 12, 2022. WORK IS IN SUPPORT OF THE EXPANSION & RECONFIGURATION PROJECT 1 AT THE SAN LUIS I LPOE. MODIFICATION IS IN THE AMOUNT OF $4,624.00. |