Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
24 actions since 2024-07-19. Each is a modification or amendment with the money it added or took back.
Date
Modification
Kind
Amount
What the agency wrote
2026-07-01
PS0023
Supplemental agreement (work within scope)
$0
DEI AUTOMOD
2026-04-27
PS0022
Supplemental agreement (work within scope)
$71.9K
THIS MODIFICATION IS BEING ISSUED FOR THE DESIGN AND CONSTRUCTION OF TEMP CROSSING AND TO REPLACE EXISTING EXTERIOR DOORS AT THE TPF FOR THE CALEXICO LPOE PHASE 2B IN CALEXICO, CA
2026-04-20
PS0021
Supplemental agreement (work within scope)
$57.5K
THIS MODIFICATION IS BEING ISSUED FOR UNFORESEEN GRADE BEAMS DURING DEMOLITION OF THE HEFFERNAN SITE AT THE CALEXICO LPOE PHASE 2B PROJECT IN CALEXICO, CA
2026-02-11
PS0019
Supplemental agreement (work within scope)
$23.9K
THIS MODIFICATION IS BEING ISSUED TO INSTALL A FIRE ALARM CONTROL PANEL AT THE TEMP PED FACILITY AT THE CALEXICO LPOE PHASE 2B PROJECT IN CALEXICO, CALIFORNIA.
2026-02-11
PA0020
Administrative change
$0
THIS ADMIN MOD IS TO CORRECT CONTRACT AMOUNT STATED IN ITEM 14 OF THE PS18 AND PS19 MODIFICATIONS
2025-12-16
PS0018
Supplemental agreement (work within scope)
$217.9K
THIS MODIFICATION IS BEING ISSUED FOR THE DESIGN AND CONSTRUCTION OF THE TELECOM PATHWAY FOR THE ISP CONDUIT AT THE CALEXICO LPOE IN CALEXICO, CA
2025-11-24
PS0017
Supplemental agreement (work within scope)
$144.3K
THIS MODIFICATION IS TO PROVIDE TEMPORARY PARKING FOR CBP FOR THE CALEXICO LPOE PHASE 2B PROJECT IN CALEXICO, CALIFORNIA.
2025-11-18
PS0016
Supplemental agreement (work within scope)
$28.92M
THIS MODIFICATION IS BEING ISSUED FOR THE CONSTRUCTION OF A PEDESTRIAN TUNNEL FOR THE CALEXICO PHASE 2B PROJECT IN CALEXICO, CALIFORNIA
2025-10-23
PS0015
Supplemental agreement (work within scope)
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
-$122.1K
THIS MODIFICATION IS BEING ISSUED TO RESCIND THE P100 AND REPLACE IT WITH THE CORE BUILDING STANDARDS DATED FEB 2025
2025-10-06
PS0014
Administrative change
$0
THIS ADMINISTRATIVE MODIFICATION IS BEING ISSUED TO REVISE HSPD-12 REQUIREMENTS TO CONFORM WITH THE HSPD-12 REQUIREMENTS.
2025-09-23
PS0013
Supplemental agreement (work within scope)
$8.91M
THIS MODIFICATION IS BEING ISSUED FOR ADDITIONAL ASBESTOS ABATEMENT IN THE PEDESTRIAN FACILITY AT THE CALEXICO LPOE PHASE 2B PROJECT IN CALEXICO, CA
2025-08-26
PC0012
Change order
$64.0K
THIS NTE MODIFICATION IS BEING ISSUED FOR WATER CONSUMPTION FEES ON THE CALEXICO PHASE 2B PROJECT LOCATED IN CALEXICO, CALIFORNIA
2025-08-04
PC0011
Change order
$8.0K
THE MODIFICATION IS AN NTE TO PAY THE GOVERNMENT'S PORTION OF THE RENT TO THE CITY OF CALEXICO
2025-07-17
PS0010
Change order definitized
-$4.3K
THIS MODIFICATION IS BEING ISSUED TO DEFINITIZE PC04 FOR UPRR COORDINATION FOR THE CALEXICO LPOE PHASE 2B IN CALEXICO, CALIFORNIA
2025-07-07
PS0009
Administrative change
$0
THIS MODIFICATION IS BEING ISSUED TO INCLUDE THE DRONE FAR CLAUSE AND TO REMOVE THE REQUIREMENT FOR AERIAL PHOTOGRAPHY.
2025-05-13
PS0008
Supplemental agreement (work within scope)
$736.9K
THIS MODIFICATION IS BEING ISSUED FOR THE DESIGN AND CONSTRUCTION OF THE NEW BORDER WALL AT THE CALEXICO LPOE PHASE 2B IN CALEXICO, CA
2025-04-03
PS0007
Supplemental agreement (work within scope)
$0
THIS MODIFICATION IS FOR THE PROHIBITION OF CERTAIN DRONES
2025-03-06
PS0006
Supplemental agreement (work within scope)
$76.0K
THIS MODIFICATION WAS ISSUED FOR THE IID POWER TO THE TEMPORARY PROCESSING SITE FOR THE CALEXICO LPOE PHASE 2B PROJECT IN CALEXICO, CALIFORNIA
2024-11-01
PS0005
Supplemental agreement (work within scope)
$1.10M
THIS MODIFICATION IS TO PROVIDE THE TUNNEL DESIGN FOR THE CALEXICO LPOE PHASE 2B PROJECT LOCATED IN CALEXICO, CA
2024-09-23
PC0004
Change order
$26.0K
THIS UNILATERAL MODIFICATION IS BEING ISSUED TO FACILITATE INVOICE PAYMENTS TO UPRR FOR DESIGN REVIEW REIMBURSEMENTS ON THE CALEXICO LPOE PHASE 2B PROJECT IN CALEXICO CA
2024-08-30
PS0003
Supplemental agreement (work within scope)
$9.0K
THIS MODIFICATION IS BEING ISSUED FOR THE PLAT AND LEGAL DESCRIPTION OF HEFFERNAN ST AT THE CALEXICO LPOE PHASE 2B PROJECT LOCATED IN CALEXICO, CA
2024-07-31
PA0002
Funding only
$0
THIS ADMIN MOD IS FOR ACCOUNTING CODE COST TRANSFER
2024-07-29
PA0001
Funding only
$0
THIS ADMINISTRATIVE MODIFICATION IS BEING ISSUED TO FIX ACCOUNTING CODES
2024-07-19
0
$173.60M
DESIGN BUILD SERVICES MODERNIZATION AND EXPANSION OF THE CALEXICO LAND PORT OF ENTRY PHASE 2B LOCATED IN CALEXICO, CALIFORNIA