47PK0125F0014↗

Elevated Technologies Services, LLC received this contract from PBS R9 Amd Capital Projects, Public Buildings Service: $3.48M obligated so far for repair or alteration of office buildings. It runs to 2028-03-21, or to 2028-05-20 if every option is exercised.

Key facts · data as of Oct 25, 2026

Recipient
Elevated Technologies Services, LLC
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS R9 Amd Capital Projects (47PK01)
Obligated to date
$3.48M
Potential value
$3.48M
Ends
2028-03-21

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 47PK0125F0014, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_47PK0125F0014_4740_47PM0024D0006_4740

BURLINGTON ELEVATOR MODERNIZATION, US POST OFFICE & COURTHOUSE, 11 ELMWOOD AVENUE, BURLINGTON, VT

Delivery Order · Public Buildings Service · to Elevated Technologies Services, LLC (UEI MYS9ZCJUSZ25) · data as of 2026-10-25

Obligated to date$3.48M3 actions
Current value$3.48Mwith options exercised
Period2025-06-30 → 2028-03-21up to 2028-05-20 with options

Up for re-bid: ends 2028-03-21. Recompete brief →

What it is

Product or service
Repair or Alteration of Office Buildings (PSC Z2AA)
Industry
Other Building Equipment Contractors (NAICS 238290)
Funded by
The Judicial Branch
Contracting office
PBS R9 Amd Capital Projects (47PK01)
Competition
Full and open competition · 2 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 47PM0024D0006
Solicitation
47PK0125R0003
Where the work is
Chittenden, VT · district VT-00

Obligations by fiscal year

FY2025$3.40M
FY2026$74.7K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

3 actions since 2025-06-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-22PS0002Supplemental agreement (work within scope)$74.7KBURLINGTON ELEVATOR MODERNIZATION, US POST OFFICE & COURTHOUSE, 11 ELMWOOD AVENUE, BURLINGTON, VT, MODIFICATION PS0002 - HOISTWAY DOOR & FRAME CHANGE ORDER
2026-09-09PS0001Supplemental agreement (work within scope)$0BURLINGTON ELEVATOR MODERNIZATION, US POST OFFICE & COURTHOUSE, 11 ELMWOOD AVENUE, BURLINGTON, VT, MODIFICATION PS0001 - NTP/ COMPLETION DATES ESTABLISHED
2025-06-300$3.40MBURLINGTON ELEVATOR MODERNIZATION, US POST OFFICE & COURTHOUSE, 11 ELMWOOD AVENUE, BURLINGTON, VT

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗