NEW O&M CONTRACTOR REQUIRED TO PROVIDE PROPOSALS FOR INITIAL DEFICIENCY ITEMS. AWARD BASED ON IDL REPAIRS AT WALSH CH, TUCSON AZ
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
6 actions since 2023-01-11. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-10-03 | PS0005 | Supplemental agreement (work within scope) | $0 | WALSH CH IDL REPAIRS - MOD TIME EXTENSION TO ASSESS THE WATER FLOW ISSUE W/ CHILLER BY A THIRD PARTY AT WALSH CH TUCSON AZ |
| 2024-07-22 | PS0004 | Supplemental agreement (work within scope) | $0 | WALSH IDL REPAIRS IN TUCSON, AZ - CHILLER REPAIR - EXTEND COMPLETION DATE. |
| 2024-02-21 | PS0003 | Supplemental agreement (work within scope) | -$329 | REMOVE SWITCHBOARD IN BASEMENT B12 REPAIR DECREASING AWARD BY $328.83. GRANT TIME EXTENSION FOR MULTI STACK CHILLER COMPLETION. |
| 2023-11-28 | PS0002 | Supplemental agreement (work within scope) | $33.4K | WALSH USCH, TUCSON, AZ, IDL REPAIRS - PRICE ERROR ADJUSTMENT ON CHILLER MULTISTACK |
| 2023-06-21 | PS0001 | Supplemental agreement (work within scope) | $0 | TIME EXTENSION DUE TO MATERIAL DELAYS. |
| 2023-01-11 | 0 | $248.1K | NEW O&M CONTRACTOR REQUIRED TO PROVIDE PROPOSALS FOR INITIAL DEFICIENCY ITEMS. AWARD BASED ON IDL REPAIRS AT WALSH CH, TUCSON AZ |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗