Putting the award page together from the records…
Putting the award page together from the records…
NEW O&M CONTRACTOR IS RESPONSIBLE FOR PROVIDING PROPOSALS FOR ITEMS FOUND ON THE INITIAL DEFICIENCY LIST. PROJECT TO COMPLETE IDL REPAIRS AT DECONCINI USCH, TUCSON AZ
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
7 actions since 2023-01-11. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-02-10 | PS0007 | Supplemental agreement (work within scope) | -$6.7K | MODIFICATION REMOVES THE REQUIREMENT OF PUMP#4 SEAL FOR THE IDL PROJECT AT DECONCINI USCH IN TUCSON AZ |
| 2024-08-26 | PS0005 | Supplemental agreement (work within scope) | $0 | TIME EXTENSION REQUEST FOR MANUFACTURER TO SHIP PART FOR INSTALLATION. |
| 2024-07-10 | PA0004 | Funding only | $0 | FY24 ACCT LINE MISTAKENLY USED A SOC REQUIRING A FIXED ASSET WHEN IT SHOULD NOT. ADMIN MOD TO CORRECT ACCOUNTING STRING. |
| 2024-03-01 | PS0003 | Supplemental agreement (work within scope) | $51.6K | REMOVE INVOICE TO REPAIR 2 SUMP PUMP AND FOR NEW PROPOSAL TO REPLACE WITH 4 SUBMERSIBLE PUMPS. TIME EXTENSION GRANTED |
| 2023-10-02 | PS0002 | Supplemental agreement (work within scope) | $0 | TIME EXTENSION UNDER FAR 52.211-13 |
| 2023-08-10 | PS0001 | Supplemental agreement (work within scope) | $0 | TIME EXTENSION FAR 52.211-13 |
| 2023-01-11 | 0 | $127.7K | NEW O&M CONTRACTOR IS RESPONSIBLE FOR PROVIDING PROPOSALS FOR ITEMS FOUND ON THE INITIAL DEFICIENCY LIST. PROJECT TO COMPLETE IDL REPAIRS AT DECONCINI USCH, TUCSON AZ |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗