INVERTER ELECTRICAL ROOM COOLING DESIGN AND BUILD COOLING FOR ELECTRICAL ROOMS THAT HOUSE BATTERY INVERTERS (9 ROOMS) AT THE 1ST STREET COURTHOUSE, LOS ANGELES, CA 90012-3100
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
8 actions since 2024-04-12. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-02 | PS0007 | Supplemental agreement (work within scope) | $24.2K | CHANGE ORDER FOR ADDITIONAL BAS CONTROLLED CHILLED WATER FAN-COIL UNITS |
| 2025-09-16 | PS0006 | Supplemental agreement (work within scope) | $0 | NO COST TIME EXTENSION |
| 2025-05-14 | PA0005 | Administrative change | $0 | UPDATE THE FUNDING FIXED ASSET RCA50581CA0323ZZ INFORMATION FROM CIPIMP TO IMPROVMNT IN THE ACCOUNTING LINES OF THIS AWARD |
| 2025-05-06 | PS0004 | Supplemental agreement (work within scope) | $0 | NO COST TIME EXTENSION |
| 2025-01-29 | PA0003 | Administrative change | $0 | ADMIN MOD TO TRANSFER TASK ORDER TO CONTRACTING OFFICER TO FANG VILAYLAK-TANTHUM |
| 2024-11-21 | PS0002 | Supplemental agreement (work within scope) | $0 | UPDATE POP DATES PER NOTICE TO PROCEED |
| 2024-05-15 | PS0001 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO CHANGE SUBSTANTIAL COMPLETION DATE TO 01/07/2024 AND TOTAL COMPLETION TO 02/16/2025 |
| 2024-04-12 | 0 | $554.9K | INVERTER ELECTRICAL ROOM COOLING DESIGN AND BUILD COOLING FOR ELECTRICAL ROOMS THAT HOUSE BATTERY INVERTERS (9 ROOMS) AT THE 1ST STREET COURTHOUSE, LOS ANGELES, CA 90012-3100 |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗