FCS REPAIR FIRE RISERS, ASPHALT VAULT LID & COVER PLATE IN FCS BUILDING IN SEATTLE, WA.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
2 subawards totaling $27.9K (26.9% of what was obligated), as P & L General Contractors, Inc. reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Looker Asphalt Inc | $14.5K | 1 | WA | 2024-08-23 | 2024-08-23 |
| Fire Systems West Inc | $13.4K | 1 | WA | 2024-08-23 | 2024-08-23 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-08-23 | Looker Asphalt Inc | $14.5K | PLACE HMA OVERLAY, PAVEMENT GRINDING. |
| 2024-08-23 | Fire Systems West Inc | $13.4K | REPLACE ONE EXISTING PIV/NRS GATE VALVE, INCLUDES DESIGN AND INSPECTION. |
2 actions since 2024-08-20. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-02-06 | PS0001 | Supplemental agreement (work within scope) | $4.1K | MODIFICATION TO ADD CDF TO STABILIZE FIRE RISER AND SURROUNDING ASPHALT AT FCS BUILDING IN SEATTLE, WA. |
| 2024-08-20 | 0 | $99.7K | FCS REPAIR FIRE RISERS, ASPHALT VAULT LID & COVER PLATE IN FCS BUILDING IN SEATTLE, WA. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗