47PL0124F0046↗
RJS Construction, Inc received this contract from PBS Project Delivery West - Branch E, Public Buildings Service: $965.2K obligated so far for repair or alteration of office buildings. Its period of performance ended 2026-10-30; options could extend it to 2026-12-31.
Key facts · data as of Nov 20, 2026
- Recipient
- RJS Construction, Inc
- Awarding agency
- Public Buildings Service (General Services Administration)
- Contracting office
- PBS Project Delivery West - Branch E (47PD55)
- Obligated to date
- $965.2K
- Potential value
- $965.2K
- Ends
- 2026-10-30
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 20, 2026.
Cite this page: SpendQuery, Award 47PL0124F0046, data as of Nov 20, 2026, https://spendquery.com/award?id=CONT_AWD_47PL0124F0046_4740_47PL0124D0010_4740
RJS Construction, Inc: all federal awards · General Services Administration: spending · PBS Project Delivery West - Branch E: what it buys · The follow-on: recompete brief
HCH USAO FLOOR 7A BUILDOUT, HATFIELD COURTHOUSE (OR0052ZZ), PORTLAND, OR
Up for re-bid: ends 2026-10-30. Recompete brief → · USBC Weinberger Lower Floor Kitchenette Upgrade ↗
What it is
- Product or service
- Repair or Alteration of Office Buildings (PSC Z2AA)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Funded by
- Department of Justice
- Contracting office
- PBS Project Delivery West - Branch E (47PD55)
- Competition
- Full and open after exclusion of sources · 6 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 47PL0124D0010
- Where the work is
- Multnomah, OR · district OR-01
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
3 subawards totaling $526.0K (54.5% of what was obligated), as RJS Construction, Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Mckinstry Co LLC | $303.8K | 1 | WA | 2025-02-04 | 2025-02-04 |
| Cushing Terrell/Imeg LLC | $121.1K | 1 | MT | 2024-09-06 | 2024-09-06 |
| Fred Shearer & Sons Inc. | $101.1K | 1 | OR | 2024-10-04 | 2024-10-04 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2025-02-04 | Mckinstry Co LLC | $303.8K | (ORIGINAL): MECHANICAL/PLUMBING/FIRE SPRINKLER/ELECTRICAL (CO1): SCOPE CHANGES/COST ESCALATION (CO2): DISCONNECT & DEMO EXISTING VA (CO3): LIGHTING DEMO |
| 2024-09-06 | Cushing Terrell/Imeg LLC | $121.1K | DESIGN SERVICES |
| 2024-10-04 | Fred Shearer & Sons Inc. | $101.1K | (ORIGINAL): FRAME/DRYWALL/PAINT/DOORS/ETC. (CO1): SCOPE CHANGES/DESIGN & COST (CO2): LABOR INCREASE (CO3): DEMO & BUILD BACK FROM BASE |
Every action
5 actions since 2024-08-15. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-21 | PS0004 | Supplemental agreement (work within scope) | $8.3K | ADD CLIN 0005 ADDITIONAL WORK TO REMOVE EXISTING LIGHT FIXTURE, STALL DRYWALL, AND ACCESS PANEL. |
| 2026-06-25 | PS0003 | Supplemental agreement (work within scope) | $4.9K | THIS MODIFICATION REPLACES THE VAV BOX TO COMPLY WITH DESIGN STANDARDS AND COMPLETE CONSTRUCTION AT MARK O HATFIELD USCH 1000 SW 3RD AVE., PORTLAND, OR 97204. |
| 2026-03-31 | PS0002 | Supplemental agreement (work within scope) | $172.9K | IN ACCORDANCE WITH THE REVISED SOW & 100% DESIGN, GSA ACCEPTS RJS CONSTRUCTION, INC.'S PROPOSAL FOR ADDITIONAL WORK INCLUDING LABOR AND MATERIAL COST INCREASES IN THE AMOUNT OF $172,854.31 FOR THE PROJECT AT 1000 SW 3RD AVE, PORTLAND, OR 92704. |
| 2025-08-21 | PS0001 | Supplemental agreement (work within scope) | $0 | GENERAL SERVICES ADMINISTRATION. 1000 SW 3RD AVE, PORTLAND, OR 97204. MODIFICATION P-1 IS TO INCORPORATE THE NEW INTERIM CORE BUILDING STANDARDS. |
| 2024-08-15 | 0 | $779.2K | HCH USAO FLOOR 7A BUILDOUT, HATFIELD COURTHOUSE (OR0052ZZ), PORTLAND, OR |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗