47PM0721F0094↗

Johnson Controls Government Systems, LLC received this contract from PBS R11 Building Services Division Center 1, Public Buildings Service: $68.07M obligated so far for special studies/analysis- building technology. It runs to 2046-04-30.

Key facts · data as of Oct 22, 2026

Recipient
Johnson Controls Government Systems, LLC
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS R11 Building Services Division Center 1 (47PM05)
Obligated to date
$68.07M
Potential value
$241.75M
Ends
2046-04-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.

Cite this page: SpendQuery, Award 47PM0721F0094, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_47PM0721F0094_4740_DEEE0008032_8900

NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION SERVICES.

Delivery Order · Public Buildings Service · to Johnson Controls Government Systems, LLC (UEI RXNUR4G46NG3) · data as of 2026-10-22

Obligated to date$68.07M16 actions
Current value$70.84Mwith options exercised
Potential value$241.75Mif every option is used
Period2021-05-01 → 2046-04-30current end date
Passed on$42.58Mto 7 subcontractors

What it is

Product or service
Special Studies/Analysis- Building Technology (PSC B540)
Industry
Engineering Services (NAICS 541330)
Contracting office
PBS R11 Building Services Division Center 1 (47PM05)
Competition
Full and open competition · 12 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under DEEE0008032

Obligations by fiscal year

FY2023$1.78M
FY2024$30.47M
FY2025$24.82M
FY2026$10.99M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

9 subawards totaling $42.58M (62.6% of what was obligated), as Johnson Controls Government Systems, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.

SubcontractorAmountSubawardsWhereFirstLast
Southern Co Services Inc$39.48M2NC2026-02-192026-03-16
Mucat Technologies, Inc.$1.92M2TN2026-05-282026-07-08
Schneider Electric Federal, Inc.$752.3K1MD2026-02-112026-02-11
James Vito Inc$157.4K1MD2023-12-072023-12-07
Onix II, Inc.$134.5K1PA2026-05-042026-05-04
Aqualogix LLC$85.0K1FL2026-05-112026-05-11
Onix, Inc.$55.9K1PA2023-04-262023-04-26
The largest single subawards
DateToAmountFor
2026-02-19Powersecure, Inc.$27.31MDECOUPLE WHC FROM GSA HOTD STEAM PLANT
2026-03-16Powersecure, Inc.$12.17MMECHANICAL- COOLING TOWER REPLACEMENT, CHILL WATER PUMP REPLACEMENT, PREP AND PAINT CT STEEL, FURNISH AND INSTALL BASIN FILTRATION SYSTEM, REPLACE BUTTERFLY VALVES, REPLACE GEAR OPERATED BUTTERFLY VALVES, AND REPLACE…
2026-05-28Mucat Technologies, Inc.$1.88MMECHANICAL, HVAC AND ELECTRICAL LABOR FOR ESPC PROJECT IN WASHINGTON DC.
2026-02-11Schneider Electric Federal, Inc.$752.3KNEOB 9TH AND 10TH FLOOR VISTA BAS REPLACEMENT. EEOB NORTH COURT COOLING TOWER REPLACEMENT.
2023-12-07James Vito Inc$157.4KPLUMBING, HEATING AND AIR CONDITIONING SERVICES
2026-05-04Onix II, Inc.$134.5KCOMMISSIONING OF FIVE (5) BOILERS IN EEOB WITH 12 PUMPS.
2026-05-11Aqualogix LLC$85.0KSCHEDULED PREVENTIVE MAINTENANCE & MONITORING SERVICES
2023-04-26Onix, Inc.$55.9KCOMMISSIONING
2026-07-08Mucat Technologies, Inc.$40.0KRRB & NEOB WATER SOFTENER SALT DELIVERING ONSITE.

Every action

16 actions since 2023-07-18. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-05-04PA0029Funding only$6.06MFUNDING MODIFICATION FOR YEAR 3 (FY2026)
2026-03-20PA0028Administrative change$0INCORPORATION OF ASSIGNMENT OF CLAIMS
2025-12-23PS0026Supplemental agreement (work within scope)$0THIS MODIFICATION DECOUPLES THE WHITE HOUSE COMPLEX FROM DISTRICT STEAM.
2025-12-12PO0025Change order$0ALLOCATION OF BASE PROJECT CONTINGENCY FUNDS.
2025-10-17PS0024Additional work (new agreement)$4.93MTHIS MODIFICATION PURCHASES NEW COOLING TOWERS FOR EISENHOWER EXECUTIVE OFFICE BUILDING, UPGRADES THE BUILDING AUTOMATION SYSTEM AND REPAIRS MULTIPLE HVAC RELATED DEFICIENCIES AT RONALD REAGAN BUILDING.
2025-07-16PA0021Administrative change$0UPDATE OF ACCOUNTING STRINGS
2025-06-06PO0017Funding only$5.96MYEAR 1 PERFORMANCE PERIOD PAYMENT.
2025-01-17PS0016Supplemental agreement (work within scope)$18.86MRRB COOLING TOWER REPLACEMENT - HPGB IRA FUNDED
2024-09-28PA0015Funding only-$40.8KDEOBLIGATE FUNDS FROM CLIN 0001 FOR COST ALLOCATION
2024-09-18PS0014Supplemental agreement (work within scope)$62.0KELECTRICAL OUTAGE SUPPORT
2024-08-21PA0012Administrative change$40.8KCOST ALLOCATION CORRECTION
2024-06-07PO0011Funding only$7.72MFUNDING FOR (YEAR 1) CONSTRUCTION PERIOD SAVINGS, PRINCIPAL AND INTERESTS, OMRR AND PERFORMANCE PERIOD SERVICES FOR MV AND MA
2024-05-15PS0010Additional work (new agreement)$0INFLATION REDUCTION ACT SIGNAGE FOR RONALD REAGAN BUILDING.
2023-11-17PS0009Supplemental agreement (work within scope)$22.69MRONALD REAGAN BUILDING ELECTRIFICATION BY INSTALLING HEAT PUMPS AND ELECTRIC BOILERS.
2023-09-29PO0008Funding only$1.65MCONSTRUCTION PERIOD SAVINGS FOR FY 23
2023-07-18PO0007Funding only$134.0KGUARANTEED UTILITY REBATES

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗