68HE0725F0119↗
Weston Solutions Inc received this contract from Region 7 Contracting Office, Environmental Protection Agency: $1.78M obligated so far for support- professional: emergency response/disaster planning/preparedness support. It runs to 2027-08-05.
Key facts · data as of Oct 26, 2026
- Recipient
- Weston Solutions Inc
- Awarding agency
- Environmental Protection Agency
- Contracting office
- Region 7 Contracting Office (68HE07)
- Obligated to date
- $1.78M
- Potential value
- $3.22M
- Ends
- 2027-08-05
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.
Cite this page: SpendQuery, Award 68HE0725F0119, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_68HE0725F0119_6800_68HE0720D0005_6800
Weston Solutions Inc: all federal awards · Environmental Protection Agency: spending · Region 7 Contracting Office: what it buys · The follow-on: recompete brief
R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2
Up for re-bid: ends 2027-08-05. Recompete brief → · R--R10 START VI: Superfund Technical Assessment & Response Team (START) VI ↗
What it is
- Product or service
- Support- Professional: Emergency Response/Disaster Planning/Preparedness Support (PSC R429)
- Industry
- Environmental Consulting Services (NAICS 541620)
- Contracting office
- Region 7 Contracting Office (68HE07)
- Competition
- Full and open competition
- Pricing
- Labor hours
- How it was bought
- Single-award IDIQ · under 68HE0720D0005
- Where the work is
- King, WA · district WA-07
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
1 subaward totaling $49.2K (2.8% of what was obligated), as Weston Solutions Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Beacon Environmental Services, Inc. | $49.2K | 1 | MD | 2025-09-05 | 2025-09-05 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2025-09-05 | Beacon Environmental Services, Inc. | $49.2K | LAB ANALYSIS SERVICES |
Every action
11 actions since 2025-07-23. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-31 | P00010 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00010: INCREASE SUBTASK #13 CEILING FOR GREATER THAN ANTICIPATED SAMPLING TO DETERMINE IF CONTAMINATION IS MIGRATING OFF SITE TO ADJACENT RESIDENCES. |
| 2026-07-07 | P00009 | Funding only | $418.1K | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00009: ADD INCREMENTAL FUNDING FOR CONTINUING SITE ASSESSMENT WORK |
| 2026-05-21 | P00008 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00008: ISSUE TWO NEW SUBTASKS (#20-21) AND SWAP FUNDS TO CORRECT ACCOUNTING LINE INFORMATION |
| 2026-04-16 | P00007 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00007: ISSUE TWO NEW SUBTASKS (#18-19) AND INCREASE SUBTASK #13 CEILING FOR GREATER THAN ANTICIPATED HAZARDOUS WASTE DISPOSAL COSTS |
| 2026-03-17 | P00006 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00006: INCREASE SUBTASK #17 CEILING FOR GREATER THAN ANTICIPATED TRAVEL COSTS |
| 2026-02-05 | P00005 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00005: ISSUE SUBTASK #17 AND INCREASE SUBTASK #7 & 8 CEILING FOR ADDITIONAL SAMPLE COLLECTION |
| 2026-01-06 | P00004 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00004: ISSUE SUBTASK #16 AND INCREASE SUBTASK #3 CEILING FOR ADDITIONAL PRIVATE SUB-SITE HRS EVALUATIONS |
| 2025-11-24 | P00003 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00003: INCREASE SUBTASK #15 CEILING FOR NECESSARY SAMPLING SUPPORTING THE PRELIMINARY ASSESSMENT |
| 2025-11-05 | P00002 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00002: ISSUE SUBTASK 15 FOR A PRELIMINARY ASSESSMENT |
| 2025-08-27 | P00001 | Supplemental agreement (work within scope) | $0 | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 MOD P00001: AMEND SUBTASKS #10-13 FOR ADDITIONAL HOURS DUE TO DELAYS IN LAB DELIVERABLES |
| 2025-07-23 | 0 | $1.36M | R10 START V: CERCLA SITE ASSESSMENT TECHNICAL SUPPORT #2 |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗