68HE0924F0102↗

CH2M Hill, Inc received this contract from Region 9 Contracting Office, Environmental Protection Agency: $17.19M obligated so far for architect and engineering- general: management engineering. It runs to 2029-09-26.

Key facts · data as of Oct 23, 2026

Recipient
CH2M Hill, Inc
Awarding agency
Environmental Protection Agency
Contracting office
Region 9 Contracting Office (68HE09)
Obligated to date
$17.19M
Potential value
$24.65M
Ends
2029-09-26

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award 68HE0924F0102, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_68HE0924F0102_6800_68HE0318D0004_6800

RAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1

Delivery Order · Environmental Protection Agency · to CH2M Hill, Inc (UEI NBG7N3TRX7K4) · data as of 2026-10-23

Obligated to date$17.19M10 actions
Current value$24.65Mwith options exercised
Period2024-09-30 → 2029-09-26current end date
Passed on$1.90Mto 6 subcontractors

What it is

Product or service
Architect and Engineering- General: Management Engineering (PSC C214)
Industry
Remediation Services (NAICS 562910)
Contracting office
Region 9 Contracting Office (68HE09)
Competition
Full and open competition · 1 offer received
Pricing
Cost plus fixed fee
How it was bought
Multiple-award IDIQ · under 68HE0318D0004
Solicitation
68HE0924R0022
Where the work is
Contra Costa, CA · district CA-10

Obligations by fiscal year

FY2024$8.21M
FY2025$5.80M
FY2026$3.18M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

21 subawards totaling $1.90M (11.0% of what was obligated), as CH2M Hill, Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.

SubcontractorAmountSubawardsWhereFirstLast
Engineering/Remediation Resources Group, Inc.$584.8K7CA2025-07-172026-04-01
Elem Indian Community$545.8K6CA2025-05-212026-01-09
Gregg Drilling, LLC$439.9K2CA2025-07-282026-02-27
Network Environmental Systems, Incorporated$134.7K2CA2025-07-232026-01-21
Geologic Associates, Inc.$105.4K2CA2025-10-032026-02-12
Bridges Restoration, LLC$85.7K2CA2025-10-302026-06-29
The largest single subawards
DateToAmountFor
2025-07-17Engineering/Remediation Resources Group, Inc.$423.7KREMEDIATION SERVICES
2025-07-28Gregg Drilling, LLC$385.4KREMEDIATION SERVICES
2025-05-21Elem Indian Community$207.3KOTHER MANAGEMENT CONSULTING SERVICES
2025-10-13Elem Indian Community$177.0KOTHER MANAGEMENT CONSULTING SERVICES
2025-07-23Network Environmental Systems, Incorporated$139.9KTESTING LABORATORIES AND SERVICES
2025-10-03Geologic Associates, Inc.$105.4KTESTING LABORATORIES AND SERVICES
2026-01-09Elem Indian Community$83.6KOTHER MANAGEMENT CONSULTING SERVICES
2025-12-10Elem Indian Community$77.9KOTHER MANAGEMENT CONSULTING SERVICES
2025-10-30Bridges Restoration, LLC$73.6KRESIDENTIAL REMODELERS
2025-09-25Engineering/Remediation Resources Group, Inc.$64.9KREMEDIATION SERVICES
2026-02-27Gregg Drilling, LLC$54.5KREMEDIATION SERVICES
2026-04-01Engineering/Remediation Resources Group, Inc.$30.5KREMEDIATION SERVICES
2025-11-07Engineering/Remediation Resources Group, Inc.$29.6KREMEDIATION SERVICES
2025-10-15Engineering/Remediation Resources Group, Inc.$16.1KREMEDIATION SERVICES
2026-02-19Engineering/Remediation Resources Group, Inc.$13.3KREMEDIATION SERVICES
2026-06-29Bridges Restoration, LLC$12.1KRESIDENTIAL REMODELERS
2025-12-23Engineering/Remediation Resources Group, Inc.$6.6KREMEDIATION SERVICES
2025-07-15Elem Indian Community$0OTHER MANAGEMENT CONSULTING SERVICES
2026-02-12Geologic Associates, Inc.$0TESTING LABORATORIES AND SERVICES
2025-08-29Elem Indian Community-$0OTHER MANAGEMENT CONSULTING SERVICES
2026-01-21Network Environmental Systems, Incorporated-$5.3KTESTING LABORATORIES AND SERVICES

Every action

10 actions since 2024-09-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-24P00009Funding only$3.18MRAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION IS TO MOD TO ADD FUNDING AND INCORPORATE THE CONTRACTORS CHANGE PROPOSAL.
2025-12-29P00008Administrative change$0RAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION IS TO MOD IN SOWA TO FIX LANGUAGE FOR CLARIFICATION AT NO ADDITIONAL COST.
2025-11-21P00007Administrative change$0RAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION IS TO ADD TOCOR
2025-09-10P00006Funding only$1.55MRAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION IS TO ADD FUNDING.
2025-08-06P00005Funding only$2.81MRAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION IS TO ADD FUNDING.
2025-07-30P00004Administrative change$0RAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION IS TO ADD AN ALTERNATE TOCOR AND CORRECT MODIFICATION 3 WORDING.
2025-07-08P00003Change order$1.44MRAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION FOR IN-SCOPE CHANGES AND BUDGET REALIGNMENT TO FUND CRITICAL PATH ACTIVITIES.
2025-03-12P00002Change order$78.5KRAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1 MODIFICATION FOR EXERCISE OF OPTIONAL TASK AND INCORPORATION OF SOWA 1
2025-02-24P00001Change order-$78.5KRAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1
2024-09-300$8.21MRAF DES TASK ORDER FOR REMEDIAL DESIGN AND REMEDIAL ACTION SUPPORT SULPHUR BANK MERCURY MINE OU1

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗