Putting the award page together from the records…
Putting the award page together from the records…
FUNDS CONSTRUCTION PROJECT ID FS NEZPR117 221(1), NATIONAL FOREST SYSTEM ROAD 221 REHABILITATION
Up for re-bid: ends 2026-10-30. Recompete brief → · WA FWS LPO MULTI(1) Little Pend Oreille NWR Culvert Improvements ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
6 actions since 2026-03-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-16 | P00005 | Supplemental agreement (work within scope) | $0 | ID FS NEZPR117 221(1) NFS ROAD 221 REHABILITATION - THIS CONTRACT MODIFICATION (CM) COVERS THE AGREEMENT BETWEEN FHWA AND MA DEATLEY (MAD) ON THE ACCEPTANCE OF CHIP SEAL LOT 1 AT AN 80% PAY FACTOR. |
| 2026-08-18 | P00004 | Funding only | $350.0K | ID FS NEZPR117 221(1) NFS ROAD 221 REHABILITATION - THIS ADMINISTRATIVE CHANGE INCREASES THE PROJECT OBLIGATION FOR ANTICIPATED FUNDING NEEDS. THE FIXED COMPLETION DATE REMAINS 8/26/2024 |
| 2026-07-28 | P00003 | Supplemental agreement (work within scope) | $0 | ID FS NEZPR117 221(1) NFS ROAD 221 REHABILITATION - HIS CONTRACT MODIFICATION (CM) AUTHORIZES TEMPORARY ROAD CLOSURES, ESTABLISHES MEASUREMENT CONVERSION METHODS FOR ROADWAY AGGREGATE ITEMS, DEFINES THE PARAMETERS FOR UTILIZING AND REPLACING THE EXIS |
| 2026-06-12 | P00002 | Supplemental agreement (work within scope) | $414.0K | ID FS NEZPR117 221(1) NFS ROAD 221 REHABILITATION -THIS CONTRACT MODIFICATION (CM) COVERS ALL COSTS ASSOCIATED WITH ADDING 1.8 MILES OF FULL DEPTH RECLAMATION WITH CEMENT, CEMENTITIOUS MATERIAL, PRIME COAT, FROM APPROXIMATE MP 6.75 TO MP 8.55. THIS |
| 2026-05-27 | P00001 | Supplemental agreement (work within scope) | $911.0K | FUNDS CONSTRUCTION PROJECT ID FS NEZPR117 221(1), NATIONAL FOREST SYSTEM ROAD 221 REHABILITATION THIS CONTRACT MODIFICATION (CM) COVERS ALL COSTS ASSOCIATED WITH ADDING 1,500 TONS OF 30510-0000 CEMENTITIOUS MATERIAL AND 2 ACRES OF 62501-0000 TUR |
| 2026-03-31 | 0 | $7.98M | FUNDS CONSTRUCTION PROJECT ID FS NEZPR117 221(1), NATIONAL FOREST SYSTEM ROAD 221 REHABILITATION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗