692M1523F00037↗

Saliense Consulting LLC received this contract from 692M15 Acquisition & Grants, Aaq600, Federal Aviation Administration: $21.25M obligated so far for support- professional: engineering/technical. It runs to 2027-07-09.

Key facts · data as of Oct 25, 2026

Recipient
Saliense Consulting LLC
Awarding agency
Federal Aviation Administration (Department of Transportation)
Contracting office
692M15 Acquisition & Grants, Aaq600 (692M15)
Obligated to date
$21.25M
Potential value
$41.27M
Ends
2027-07-09

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 692M1523F00037, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_692M1523F00037_6920_47QRAA18D00C0_4732

THE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS

Delivery Order · Federal Aviation Administration · to Saliense Consulting LLC (UEI WM5MB479LXD3) · data as of 2026-10-25

Obligated to date$21.25M34 actions
Current value$21.25Mwith options exercised
Potential value$41.27Mif every option is used
Period2023-07-07 → 2027-07-09current end date

Up for re-bid: ends 2027-07-09. Recompete brief →

What it is

Product or service
Support- Professional: Engineering/Technical (PSC R425)
Industry
Administrative Management and General Management Consulting Services (NAICS 541611)
Contracting office
692M15 Acquisition & Grants, Aaq600 (692M15)
Competition
Full and open competition · 13 offers received
Pricing
Time and materials
How it was bought
GSA Schedule · under 47QRAA18D00C0
Where the work is
Fairfax, VA · district VA-11

Obligations by fiscal year

FY2023$3.97M
FY2024$5.06M
FY2025$5.36M
FY2026$6.86M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

34 actions since 2023-07-07. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-03P00033Funding only$296.8KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2026-08-17P00032Funding only$214.3KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2026-08-06P00031Funding only$2.78MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2026-06-29P00030Option exercised$1.90MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2026-04-14P00029Funding only$1.50MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2026-03-18P00028Funding only$172.0KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-12-22P00027Administrative change$0THE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-12-18P00026Administrative change$0THE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-08-26P00025Funding only$1.00MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-08-21P00024Funding only$35.0KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-08-14P00023Funding only$560.0KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-07-28P00022Funding only$161.6KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-07-22P00021Funding only$35.4KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-07-16P00020Funding only$12.4KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-06-09P00019Option exercised$1.81MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-01-24P00018Funding only$35.0KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-01-22P00017Funding only$1.57MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-01-15P00016Funding only$35.0KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2025-01-02P00015Funding only$35.4KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-11-05P00014Funding only$70.3KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-08-26P00013Funding only$145.4KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-08-06P00012Funding only$35.0KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-07-29P00011Funding only$1.74MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-07-18P00010Funding only$64.1KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-07-09P00009Funding only$35.4KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-06-27P00008Funding only$1.70MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-06-18P00007Option exercised$0THE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-04-26P00006Funding only$35.0KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-03-27P00005Funding only$35.4KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-03-04P00004Funding only$1.23MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2024-02-16P00003Funding only$35.4KTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2023-09-11P00002Funding only$0THE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2023-08-24P00001Supplemental agreement (work within scope)$2.88MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS
2023-07-070$1.09MTHE CONTRACTOR MUST PROVIDE IS&P SUPPORT TO THE COMPLIANCE DIVISION OF THE IS&P ORGANIZATION AS IDENTIFIED IN THE STATEMENT OF WORK (SOW). THE FOLLOWING TASK REQUIREMENTS MUST BE SUPPORTED BY THE CONTRACTOR: PROGRAM MANAGEMENT SUPPORT IS

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗