PROJECT NP-EVER 219(1), 222(1): THE PROJECT CONSISTS OF THE ASPHALT PAVEMENT MILLING AND OVERLAY, ASPHALT PAVEMENT PATCHING, PAVEMENT MARKING, RAISED PAVEMENT MARKER, CULVERT AND MANHOLE REPLACEMENT, REMOVE AND REST INLET FRAME AND GRATE, REPLACEMEN
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
5 actions since 2022-10-03. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-03-12 | P00007 | Close-out | $0 | NP-EVER 219(1), 222(1) THE PURPOSE OF MODIFICATION IS TO FINANCIALLY AND CONTRACTUALLY CLOSE THIS TASK ORDER CONTRACT IN ITS ENTIRETY IN THE AMOUNT OF $2,276,874.70. |
| 2023-05-17 | P00006 | Funding only | $0 | NP-EVER 219(1), 222(1) 693C7320D000015/693C7321F000109 CM #6 NO CHANGE TO CONTRACT AMOUNT NO CHANGE TO CONTRACT TIME |
| 2023-05-01 | P00005 | Funding only | -$117.6K | NP-EVER 219(1), 222(1) 693C7320D000015/693C7321F000109 CM #5 DECREASE CONTRACT AMOUNT BY $117,635.80 EXTEND CONTRACT TIME BY 6 CALENDAR DAYS FINALIZE EXISTING QUANTITIES |
| 2023-03-01 | P00004 | Administrative change | $0 | NP-EVER 219(1), 222(1) CM #4 NO CHANGE TO CONTRACT AMOUNT NO CHANGE TO CONTRACT TIME EXTEND PERIOD OF PERFORMANCE TO MARCH 31, 2024 |
| 2022-10-03 | P00003 | Administrative change | $0 | NP-EVER 219(1), 222(1) CM #3 NO CHANGE TO CONTRACT AMOUNT NO CHANGE TO CONTRACT TIME EXTEND PERIOD OF PERFORMANCE TO MARCH 31, 2023 |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗