Maymead Inc received this contract from 693C73 Eastern Fed Lands Division, Federal Highway Administration: $18.19M obligated so far for construction of highways, roads, streets, bridges, and railways. It runs to 2027-09-30.
Key facts · data as of Oct 22, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.
Cite this page: SpendQuery, Award 693C7322C000009, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_693C7322C000009_6925_-NONE-_-NONE-
Maymead Inc: all federal awards · Department of Transportation: spending · 693C73 Eastern Fed Lands Division: what it buys · The follow-on: recompete brief
PROJECT NP-BLRI 2B13, 2H17, ETC: THE PROJECT CONSISTS OF THE RECONSTRUCTION AND REHABILITATION OF THE BLUE RIDGE PARKWAY IN NORTH CAROLINA FROM MILEPOST 229.6 TO MP 305.1, INCLUDING OVERLOOKS, PARKING AREAS AND RAMPS. WORK ALSO INCLUDES DRAINAGE ASS
Up for re-bid: ends 2027-09-30. Recompete brief → · Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY25(2) ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
11 actions since 2024-05-30. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-12 | P00012 | Funding only | $6.52M | NP-BLRI 2B13, 2H17, ETC. - CM #12: 693C7322C000009 THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) INCREASE THE CONTRACT AMOUNT BY $6,522,020.10 FROM $109,631,533.52 TO $116,153,553.62. 2) ADD NEW SCHEDULE R TO THE CONTRACT. 3) PROVIDE FO |
| 2026-07-01 | P00011 | Funding only | -$20 | NP-BLRI 2B13, 2H17, ETC. - CM #11: 693C7322C000009 THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) DECREASE THE CONTRACT AMOUNT BY $19.76 FROM $109,631,553.28 TO $109,631,533.52. 2) ADD 261-CALENDAR DAYS DUE TO VARIOUS DELAYS. 3) ADD NEW PA |
| 2026-05-21 | P00010 | Funding only | $2.23M | NP-BLRI 2B13, 2H17, ETC. - CM #10: 693C7322C000009 THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1. ADD SCHEDULE Q TO THE CONTRACT: INCORPORATE NEW WORK FOR THE EMBANKMENT SLIDE REPAIR AT MILEPOST 318.85 RESULTING FROM HURRICANE HELENE. 2. IN |
| 2026-03-02 | P00009 | Funding only | $1.83M | NP-BLRI 2B13, 2H17, ETC. - CM #9: 693C7322C000009 THE PURPOSE OF THIS BILATERAL CONTRACT MODIFICATION IS TO: 1) INCREASE CONTRACT AMOUNT BY $1,827,525.21 FROM $105,570,222.73 TO $107,397,747.94. 2) ADD SCHEDULE P TO THE CONTRACT: INCORPORATE SLO |
| 2025-08-15 | P00008 | Funding only | $1.42M | NP-BLRI 2B13, 2H17, ETC. 693C7322C000009 CM #8 INCREASE CONTRACT AMOUNT BY $1,416,152.35 NO CHANGE TO CONTRACT TIME |
| 2025-06-30 | P00007 | Funding only | $749.3K | NP-BLRI 2B13, 2H17, ETC. 693C7322C000009 CM #7 INCREASE CONTRACT AMOUNT BY $749,285.00 NO CHANGE TO CONTRACT TIME |
| 2025-05-27 | P00006 | Funding only | $910.3K | NP-BLRI 2B13, 2H17, ETC. 693C7322C000009 CM #6 INCREASE CONTRACT AMOUNT BY $910,310.03 NO CHANGE TO CONTRACT TIME |
| 2025-01-31 | P00005 | Funding only | $4.53M | NP-BLRI 2B13, 2H17, ETC. 693C7322C000009 CM #5 INCREASE CONTRACT AMOUNT BY $4,534,881.90 NO CHANGE TO CONTRACT TIME |
| 2024-11-19 | P00004 | Funding only | -$5 | NP-BLRI 2B13, 2H17, ETC. 693C7322C000009 CM #4 DECREASE CONTRACT AMOUNT BY $4.85 EXTEND CONTRACT TIME BY 196 CALENDAR DAYS |
| 2024-09-04 | P00003 | Funding only | -$15 | NP-BLRI 2B13, 2H17, ETC. 693C7322C000009 CM #3 DECREASE CONTRACT AMOUNT BY $15.16 NO CHANGE TO CONTRACT TIME |
| 2024-05-30 | P00002 | Funding only | -$71 | NP-BLRI 2B13, 2H17, ETC. 693C7322C000009 CM #2 DECREASE CONTRACT AMOUNT BY $70.69 NO CHANGE TO CONTRACT TIME |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗