PROJECT FW-GRCO TRL(1): THE PROJECT CONSISTS OF REPLACING THE DAMAGED BOARDWALK ON HEADQUARTERS BOARDWALK TRAIL. THE WORK INCLUDES DESIGN SERVICES, TIMBER PILE AND TIMBER BOARDWALK CONSTRUCTION, AND OTHER MISCELLANEOUS WORK.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2023-03-03. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-07-17 | P00003 | Close-out | $0 | THE PURPOSE OF THIS NO COST ADMINISTRATIVE MODIFICATION IS TO FINANCIALLY AND CONTRACTUALLY CLOSE THIS TASK ORDER IN ITS ENTIRETY IN THE AMOUNT OF $1,730,805.70. |
| 2024-03-28 | P00002 | Funding only | -$22.4K | FW-GRCO TRL(1) 693C7320D000007/693C7323F00031N CM #2 DECREASE CONTRACT AMOUNT BY $22,364.30 NO CHANGE TO CONTRACT TIME FINALIZE THE EXISTING QUANTITIES |
| 2024-01-03 | P00001 | Administrative change | $0 | FW-GRCO TRL(1) 693C7320D000007/693C7323F00031N CM #1 NO CHANGE TO CONTRACT AMOUNT NO CHANGE TO CONTRACT TIME EXTEND PERIOD OF PERFORMANCE TO DECEMBER 31, 2025 |
| 2023-03-03 | 0 | $1.75M | PROJECT FW-GRCO TRL(1): THE PROJECT CONSISTS OF REPLACING THE DAMAGED BOARDWALK ON HEADQUARTERS BOARDWALK TRAIL. THE WORK INCLUDES DESIGN SERVICES, TIMBER PILE AND TIMBER BOARDWALK CONSTRUCTION, AND OTHER MISCELLANEOUS WORK. |