PROJECT PR ER DOT PRMNT RPR(15): THE PROJECT CONSISTS OF REPAIRING LANDSLIDES CAUSED BY HURRICANES IRMA AND MARIA ON PR-152R KM 1.2; AND PR-152 KM1.2, 3.05, 3.4, 3.1, AND 5.30-5.40 IN THE MUNICIPALITY OF BARRANQUITAS, PUERTO RICO. THE WORK INCLUDES,
Up for re-bid: ends 2028-08-29. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2024-01-22. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-12 | P00003 | Administrative change | $0 | PROJECT PR ER DOT PRMNT RPR(15): THE PURPOSE OF THIS NO COST MODIFICATION IS TO INCORPORATE NEW FAR CLAUSE 52.222-90 - ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS (APR 2026) (DEVIATION APR 2026) PURSUANT TO EXECUTIVE ORDER (E.O.) 14398. |
| 2026-06-04 | P00002 | Funding only | $181.5K | PR ER DOT PRMNT RPR(15) CM #2: 693C7324C000005 THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) INCREASE CONTRACT AMOUNT BY $181,487.13 FROM $8,067,513.67 TO $8,249,000.80. 2) EXTEND CONTRACT TIME BY 54 DAYS. 3) ADD NEW PAY ITEMS ASSOCIATED |
| 2026-02-03 | P00001 | Funding only | $173.6K | PR ER DOT PRMNT RPR (15) CM #1 INCREASE CONTRACT AMOUNT BY $173,628.99 EXTEND CONTRACT TIME BY 25 CALENDAR DAY |
| 2024-01-22 | 0 | $7.89M | PROJECT PR ER DOT PRMNT RPR(15): THE PROJECT CONSISTS OF REPAIRING LANDSLIDES CAUSED BY HURRICANES IRMA AND MARIA ON PR-152R KM 1.2; AND PR-152 KM1.2, 3.05, 3.4, 3.1, AND 5.30-5.40 IN THE MUNICIPALITY OF BARRANQUITAS, PUERTO RICO. THE WORK INCLUDES, |