PROJECT MS NP NATR 3P27: THE PROJECT CONSISTS OF MILLING AND OVERLAY OF MULTI-USE TRAILS, ASPHALT CONCRETE REHABILITATION, AGGREGATE SURFACING, MINOR TRAIL PROFILE ADJUSTMENTS, AND OTHER MISCELLANEOUS WORK.
Up for re-bid: ends 2027-09-30. Recompete brief → · Acadia National Park ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
3 actions since 2024-11-21. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-01 | P00002 | Funding only | $182.3K | MS NP NATR 3P27 CM #2: 693C7320D000008/693C7325F00010N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1. INCREASE CONTRACT AMOUNT FROM $2,721,278.25 BY $182,277.65 TO $2,903,555.90. 2. ADJUST CONTRACT QUANTITIES TO ENSURE THE CONTRACT MATCH |
| 2025-09-16 | P00001 | Funding only | $900.0K | MS NP NATR 3P27 693C7320D000008/693C7325F00010N CM #1 INCREASE CONTRACT AMOUNT BY $900,000.00 EXTEND CONTRACT TIME BY 167 CALENDAR DAYS |
| 2024-11-21 | 0 | $1.82M | PROJECT MS NP NATR 3P27: THE PROJECT CONSISTS OF MILLING AND OVERLAY OF MULTI-USE TRAILS, ASPHALT CONCRETE REHABILITATION, AGGREGATE SURFACING, MINOR TRAIL PROFILE ADJUSTMENTS, AND OTHER MISCELLANEOUS WORK. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗