PROJECT TN ERFO FS 2019-1(2): THE PROJECT CONSISTS OF RECONSTRUCTING SINK MOUNTAIN LAUNCH ROAD AND CONSTRUCTING A NEW PARKING AREA. THE WORK INCLUDES CLEARING AND GRUBBING, EMBANKMENT CONSTRUCTION, ASPHALT PAVEMENT, REINFORCED CONCRETE BOX CULVERT I
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
6 actions since 2024-12-05. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-12 | P00005 | Close-out | $0 | THE PURPOSE OF THIS NO COST ADMINISTRATIVE MODIFICATION IS TO FINANCIALLY AND CONTRACTUALLY CLOSE THIS TASK ORDER CONTRACT IN ITS ENTIRETY IN THE AMOUNT OF $3,181,074.58. |
| 2026-05-18 | P00004 | Funding only | -$2.2K | TN ERFO FS 2019-1(2) - CM #4: 693C7320D000008/693C7325F00013N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) DECREASE CONTRACT AMOUNT BY $2,226.99 FROM $3,183,301.57 TO $3,181,074.58. 2) ADDRESS FINAL QUANTITY ADJUSTMENTS AFTER SITE CONSTR |
| 2026-01-07 | P00003 | Administrative change | $0 | TN ERFO FS 2019-1(2) - CM #3: 693C7320D000008/693C7325F00013N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) EXTEND THE PERIOD OF PERFORMANCE TO FEBRUARY 28, 2027. 2) CHANGE THE CONTRACT SPECIFICATIONS TO ADD THE FOLLOWING TO 101.04: PERI |
| 2025-08-26 | P00002 | Funding only | $439.8K | TN ERFO FS 2019-1(2) 693C7320D000008/693C7325F00013N CM #2 INCREASE CONTRACT AMOUNT BY $439,831.41 NO CHANGE TO CONTRACT TIME |
| 2025-04-28 | P00001 | Funding only | $646.5K | TN ERFO FS 2019-1(2) 693C7320D000008/693C7325F00013N CM #1 INCREASE CONTRACT AMOUNT BY $646,533.00 NO CHANGE TO CONTRACT TIME THE TOTAL AMOUNT OF THE CONTRACT IS HEREBY INCREASED BY $646,533.00 FROM $2,096,937.16 TO $2,743,470.16. |
| 2024-12-05 | 0 | $2.10M | PROJECT TN ERFO FS 2019-1(2): THE PROJECT CONSISTS OF RECONSTRUCTING SINK MOUNTAIN LAUNCH ROAD AND CONSTRUCTING A NEW PARKING AREA. THE WORK INCLUDES CLEARING AND GRUBBING, EMBANKMENT CONSTRUCTION, ASPHALT PAVEMENT, REINFORCED CONCRETE BOX CULVERT I |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗