NC ERFO NP BLRI 2024-1(2): THE PROJECT CONSISTS OF STABILIZING DAMAGE TO THE BLUE RIDGE PARKWAY CAUSED BY HURRICANE HELENE. THE WORK INCLUDES STABILIZING AN EMBANKMENT WITH NC DOT SHOT ROCK, INSTALLING GEOMEMBRANE WITH SANDBAGS, PLACING BARRIERS TO
Up for re-bid: ends 2027-10-31. Recompete brief → · Acadia National Park ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2024-12-23. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-10 | P00003 | Administrative change | $0 | NC ERFO NP BLRI 2024-1(2) - CM #3: 693C7320D000015/693C7325F00021N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) EXTEND THE PERIOD OF PERFORMANCE FOR NC ERFO NP BLRI 2024-1(2) TO OCTOBER 31, 2027. ALL OTHER TERMS AND CONDITIONS REMAIN |
| 2025-09-17 | P00002 | Administrative change | $0 | NC ERFO NP BLRI 2024-1(2) 693C7320D000015/693C7325F00021N CM #2 NO CHANGE TO CONTRACT AMOUNT NO CHANGE TO CONTRACT TIME EXTEND PERIOD OF PERFORMANCE TO OCTOBER 31, 2026 |
| 2025-07-23 | P00001 | Funding only | $49.2K | NC ERFO NP BLRI 2024-1(2) 693C7320D000015/693C7325F00021N CM #1 INCREASE CONTRACT AMOUNT BY $49,200.00 NO CHANGE TO CONTRACT TIME |
| 2024-12-23 | 0 | $2.23M | NC ERFO NP BLRI 2024-1(2): THE PROJECT CONSISTS OF STABILIZING DAMAGE TO THE BLUE RIDGE PARKWAY CAUSED BY HURRICANE HELENE. THE WORK INCLUDES STABILIZING AN EMBANKMENT WITH NC DOT SHOT ROCK, INSTALLING GEOMEMBRANE WITH SANDBAGS, PLACING BARRIERS TO |