PROJECT NC ERFO NP BLRI 2024-1(3): THE PROJECT CONSISTS OF REPAIRING DAMAGE TO THE BLUE RIDGE PARKWAY CAUSED BY HURRICANE HELENE. THE WORK INCLUDES A SLIDE REPAIR WITH REINFORCED SOIL SLOPE (RSS), MINIMAL TREE REMOVAL FOR ACCESS, DITCH RECONDITIONIN
Up for re-bid: ends 2027-11-30. Recompete brief → · Acadia National Park ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
8 actions since 2024-12-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-06 | P00007 | Funding only | -$1.94M | NC ERFO NP-BLRI 2024-1(3) - CM #7: 693C7320D000015/693C7325F00025N THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO: 1) DECREASE CONTRACT AMOUNT BY $1,941,973.80 FROM $6,808,135.00 TO $4,866,161.20. 2) ADJUST THE FINAL QUANTITIES OF CONTRACT |
| 2025-10-15 | P00006 | Administrative change | $0 | PROJECT: NC ERFO NP BLRI 2024-1(3) - CONTRACT MODIFICATION #6 THE PURPOSE OF THIS MODIFICATION IS TO: 1) EXTEND PERIOD OF PERFORMANCE TO NOVEMBER 30, 2027 ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2025-09-08 | P00005 | Funding only | -$1.20M | NC ERFO NP-BLRI 2024-1(3) 693C7320D000015/693C7325F00025N CM #5 DECREASE CONTRACT AMOUNT BY $1,200,010.00 NO EFFECT ON CONTRACT TIME |
| 2025-07-23 | P00004 | Funding only | $2.82M | NC ERFO NP-BLRI 2024-1(3) 693C7320D000015/693C7325F00025N CM #4 INCREASE CONTRACT AMOUNT BY $2,820,000.00 EXTEND CONTRACT TIME TO AUGUST 8, 2025 |
| 2025-07-07 | P00003 | Administrative change | $100.0K | NC ERFO NP BLRI 2024-1(3) 693C7320D000015/693C7325F00025N CM #3 ADMINISTRATIVE CM TO SHOW CONTRACT INCREASE AMOUNT OF $100,000.00 FOR LINE 00101 |
| 2025-07-07 | P00002 | Funding only | $241.4K | NC ERFO NP-BLRI 2024-1(3) 693C7320D000015/693C7325F00025N CM #2 INCREASE CONTRACT AMOUNT BY $241,425.00 NO CHANGE TO CONTRACT TIME |
| 2025-04-16 | P00001 | Funding only | $0 | NC ERFO NP BLRI 2024-1(3) 693C7320D000015/693C7325F00025N CM #1 INCREASE CONTRACT AMOUNT BY $100,000.00 NO CHANGE TO CONTRACT TIME |
| 2024-12-31 | 0 | $4.85M | PROJECT NC ERFO NP BLRI 2024-1(3): THE PROJECT CONSISTS OF REPAIRING DAMAGE TO THE BLUE RIDGE PARKWAY CAUSED BY HURRICANE HELENE. THE WORK INCLUDES A SLIDE REPAIR WITH REINFORCED SOIL SLOPE (RSS), MINIMAL TREE REMOVAL FOR ACCESS, DITCH RECONDITIONIN |