Kci Technologies, Inc. received this contract from 693C73 Eastern Fed Lands Division, Federal Highway Administration: $279.2K obligated so far for architect and engineering- general: inspection (non-construction). Its period of performance ended 2026-05-31.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 693C7325F00047N, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_693C7325F00047N_6925_693C7322D000005_6925
Kci Technologies, Inc.: all federal awards · Department of Transportation: spending · 693C73 Eastern Fed Lands Division: what it buys
THE PURPOSE OF THIS CONTRACT ACTION IS TO PROCURE THE SERVICES OF CONSTRUCTION INSPECTION SERVICES, CONSTRUCTION INSPECTOR LEVEL II FOR PROJECT NP SER PMS FY24(1)- CANAVERAL NATIONAL SEASHORE. THIS ACTION IS IN COMPLIANCE WITH 23 U.S.C. 109 AND ITS I
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2025-04-03. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-15 | P00003 | Close-out | -$48.8K | THE PURPOSE OF THIS TASK ORDER MODIFICATION IS TO: 1. INCREASE CLIN 30101 - CONSTRUCTION INSPECTOR LV-II - REGULAR HOURS, OBLIGATED AMOUNT FROM $236,043.65 BY $16,055.48 TO $252,099.13 TO REFLECT CHANGES IN HOURS FROM 2,095.00 HOURS BY 143 HOURS T |
| 2026-02-10 | P00002 | Change order | $126.0K | THE PURPOSE OF THIS MODIFICATION IS TO: 1. INCREASE CLIN 30101 - CONSTRUCTION INSPECTOR LV -II (REGULAR HOURS) OBLIGATED AMOUNT FROM $135,204.00 BY $100,839.65 TO $236,043.65 TO REFLECT CHANGES IN HOURS FROM 1,200.00 HOURS BY 895 HOURS TO 2,095 HO |
| 2025-10-29 | P00001 | Change order | $0 | THE PURPOSE OF THIS NO COST MODIFICATION IS TO: 1. EXTEND THE PERIOD OF PERFORMANCE END DATE BY 150 CALENDAR DAYS, FROM NOVEMBER 1, 2025, TO MARCH 31, 2026, IN ORDER TO CONTINUE PROVIDING INSPECTION SERVICES THROUGH THE COMPLETION OF PROJECT: NP SER |
| 2025-04-03 | 0 | $202.0K | THE PURPOSE OF THIS CONTRACT ACTION IS TO PROCURE THE SERVICES OF CONSTRUCTION INSPECTION SERVICES, CONSTRUCTION INSPECTOR LEVEL II FOR PROJECT NP SER PMS FY24(1)- CANAVERAL NATIONAL SEASHORE. THIS ACTION IS IN COMPLIANCE WITH 23 U.S.C. 109 AND ITS I |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗