693JJ625F00028N↗

Kimley-Horn and Associates Inc received this contract from 693Jj6 Federal Railroad Admin, Federal Railroad Administration: $14.81M obligated so far for support- professional: engineering/technical. It runs to 2029-01-31.

Key facts · data as of Oct 26, 2026

Recipient
Kimley-Horn and Associates Inc
Awarding agency
Federal Railroad Administration (Department of Transportation)
Contracting office
693Jj6 Federal Railroad Admin (693JJ6)
Obligated to date
$14.81M
Potential value
$14.81M
Ends
2029-01-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.

Cite this page: SpendQuery, Award 693JJ625F00028N, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_693JJ625F00028N_6930_GS10F0501X_4732

NEW YORK PENN STATION SERVICE OPTIMIZATION STUDY

Delivery Order · Federal Railroad Administration · to Kimley-Horn and Associates Inc (UEI V8PKGG6NLKV6) · data as of 2026-10-26

Obligated to date$14.81M4 actions
Current value$14.81Mwith options exercised
Period2025-09-29 → 2029-01-31current end date

What it is

Product or service
Support- Professional: Engineering/Technical (PSC R425)
Industry
Engineering Services (NAICS 541330)
Contracting office
693Jj6 Federal Railroad Admin (693JJ6)
Competition
Full and open competition · 1 offer received
Pricing
Firm fixed price
How it was bought
GSA Schedule · under GS10F0501X
Solicitation
693JJ625Q000027
Funding law
Infrastructure law (IIJA)

Obligations by fiscal year

FY2025$13.58M
FY2026$1.23M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

4 actions since 2025-09-24. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-22P00003Supplemental agreement (work within scope)$857.9KNEW YORK PENN STATION SERVICE OPTIMIZATION STUDY MODIFICATION - UPDATES TO PWS
2026-07-07P00002Supplemental agreement (work within scope)$375.4KMODIFICATION TO ADD FUNDS FOR ADDITIONAL WORK - NEW YORK PENN STATION SERVICE OPTIMIZATION STUDY MODIFICATION
2026-07-07P00001Administrative change$0THE PURPOSE OF THIS MODIFICATION SERVES TO ADD THE REVISED TAR CLAUSE (TAR CLASS DEVIATION (CD) 2025-02) FOR INVOICING PAYMENT TO ALL NEW AND EXISTING CONTRACTS/ORDERS VIA BILATERAL MODIFICATION, THE CONTRACTOR CERTIFIES THAT, BY SUBMITTING THIS I
2025-09-240$13.58MNEW YORK PENN STATION SERVICE OPTIMIZATION STUDY

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗