PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE.
Up for re-bid: ends 2026-10-31. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
10 actions since 2025-05-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-22 | P00009 | Administrative change | $311.45M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2026-09-01 | P00008 | Administrative change | $121.67M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2026-05-27 | P00007 | Administrative change | $49.92M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2026-04-28 | P00006 | Administrative change | $57.49M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2026-01-29 | P00005 | Funding only | $18.00M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2025-12-04 | P00004 | Administrative change | $18.22M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2025-10-28 | P00003 | Supplemental agreement (work within scope) | $1.76M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2025-09-24 | P00002 | Administrative change | $8.10M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2025-08-04 | P00001 | Administrative change | $3.00M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |
| 2025-05-13 | 0 | $4.00M | PROJECT LIFT VCS LETTER CONTRACT FOR MODERNIZATION OF FAA VCS' IN THE NAS WHICH INCLUDES REPLACEMENT OF VCS' DEPENDENT ON TDM TECHNOLOGY TO VCS' THAT ARE IP CAPABLE. |