IIJA (ZMP) MINNEAPOLIS ARTCC - COMBINED PHASE I & II MOBILE POWER INSTALLATION, ACEPS II TEMPORARY POWER INSTALL, PER VENDOR PROPOSAL 25BX58.00, DATED 8/29/2025.
Up for re-bid: ends 2026-12-31. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
6 actions since 2025-09-09. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-17 | P00005 | Supplemental agreement (work within scope) | $136.6K | MC DEAN WILL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, TOOLS, SUPERVISION, AND DOCUMENTATION NECESSARY TO COMPLETE THE CUTOVER IDENTIFIED IN THE SCOPE OF WORK TITLED "ZMP ACEPS II TEMPORARY SYSTEM CUTOVER". IIJA JCN 1006714 |
| 2026-08-14 | P00004 | Supplemental agreement (work within scope) | $70.7K | M.C. DEAN WILL FURNISH THE MANPOWER, TOOLS, MATERIAL, AND EQUIPMENT TO REWORK THE EXISTING DLO CONDUCTOR TERMINATIONS AT VARIOUS POINTS WITHIN THE TEMPORARY POWER SYSTEM FOR THE ACEPS II PHASE 2 TEMP 2 OPERATIONS AT THE ZMP ARTCC. THIS INCLUDES AREAS |
| 2026-08-03 | P00003 | Supplemental agreement (work within scope) | $12.7K | CHANGE ORDER FOR MC DEAN TO DESIGN AND INSTALL ALL LABOR, MATERIALS, EQUIPMENT, TOOLS, SUPERVISION, TESTING, AND DOCUMENTATION NECESSARY TO MODIFY THE EXISTING FUEL SUPPLY AND RETURN PIPING ASSOCIATED WITH THE ZMP ARTCC ACEPS TEMP 2 EMERGENCY GENERAT |
| 2026-06-09 | P00002 | Supplemental agreement (work within scope) | $160.0K | CHANGE ORDER FOR MC DEAN TO DESIGN AND INSTALL THE MISSING FUEL CONTROL SYSTEM AS PART OF THE ZMP ARTCC TEMPORARY TRAILER INSTALLATION. JCN: 1006714 |
| 2025-09-24 | P00001 | Change order | $114.6K | IIJA (ZMP) MINNEAPOLIS ARTCC - COMBINED PHASE I & II MOBILE POWER INSTALLATION, ACEPS II TEMPORARY POWER INSTALL, PER VENDOR PROPOSAL 25BX58.00, DATED 8/29/2025. |
| 2025-09-09 | 0 | $5.28M | IIJA (ZMP) MINNEAPOLIS ARTCC - COMBINED PHASE I & II MOBILE POWER INSTALLATION, ACEPS II TEMPORARY POWER INSTALL, PER VENDOR PROPOSAL 25BX58.00, DATED 8/29/2025. |