CA ERFO FS LSPDR 2023-1(1) BLACK MOUNTAIN ROAD - CONSTRUCTION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
5 actions since 2025-12-29. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-17 | P00004 | Supplemental agreement (work within scope) | $399.9K | THIS CONTRACT MODIFICATION (CM) ADDS AN AMOUNT OF $399,867.90 TO THE CONTRACT AMOUNT FOR ADDITIONAL WORK REQUESTED BY THE STAKEHOLDER. THE CONTRACT COMPLETION DATE OF JUNE 26, 2026 WILL REMAIN THE SAME. |
| 2026-05-21 | P00003 | Supplemental agreement (work within scope) | $944.5K | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE FUNDS TO COVER ADDITIONAL WORK. THE COMPLETION DATE WILL BE EXTENDED FROM JUNE 12, 2026, TO JUNE 26, 2026, TO ACCOMMODATE THE ADDITIONAL WORK. |
| 2026-05-07 | P00002 | Administrative change | $0 | CA ERFO FS LSPDR 2023-1(1) BLACK MOUNTAIN ROAD - CONSTRUCTION THE PURPOSE OF THIS MODIFICATION IS TO REVERSE THE ADMINISTRATIVE MODIFICATION THAT WAS PROCESSED AS CM00001. |
| 2026-05-06 | P00001 | Administrative change | $0 | THIS MODIFICATION ADDS A NEW PROJECT FUND ACCOUNT AND MOVES A PORTION OF EXISTING PROJECT FUNDS INTO THE NEW ACCOUNT. THIS IS A NET $0.00 CHANGE. |
| 2025-12-29 | 0 | $2.75M | CA ERFO FS LSPDR 2023-1(1) BLACK MOUNTAIN ROAD - CONSTRUCTION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗