PHASE TWO DESIGN/BUILD CONTRACT FOR THE NIAGARA FALLS BORDER PATROL STATION.
Up for re-bid: ends 2026-09-08. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
7 subawards totaling $19.34M (77.6% of what was obligated), as Borealis Enterprises LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Venergy Group LLC | $16.46M | 1 | FL | 2024-01-15 | 2024-01-15 |
| SRM Group, LLC | $1.26M | 1 | VA | 2025-12-22 | 2025-12-22 |
| BRC International Corporation | $780.0K | 2 | VA | 2023-12-18 | 2026-09-15 |
| Larson Design Group, Inc | $454.0K | 1 | PA | 2023-10-19 | 2023-10-19 |
| Worldwide Structural Fabrication | $334.8K | 1 | IN | 2024-03-20 | 2024-03-20 |
| Worldwide Communications Consultants, Inc | $45.6K | 1 | IN | 2026-09-11 | 2026-09-11 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-01-15 | Venergy Group LLC | $16.46M | THE SUBCONTRACT IS BASED ON COLLABORATIVELY DRAWINGS. THE DESIGNED SOLUTION PROVIDES FOR FULLY FUNCTIONAL SYSTEMS THAT MEET THE MINIMUM REQUIREMENTS OF THE OWNER AND COMPLIANCE WITH THE ELECTRICAL CODE. INSTALLATIONS… |
| 2025-12-22 | SRM Group, LLC | $1.26M | SUPPLY ALL FURNITURE'S, FIXTURES AND EQUIPMENT INCLUDING BUT NOT LIMITED TO ALL LABOR, SUBMITTAL, SHOP DRAWINGS, MATERIAL / EQUIPMENT STORAGE, SETUP AND TRAINING AS LISTED WITHIN THEIR THE SOLICITATION NO.… |
| 2023-12-18 | BRC International Corporation | $643.9K |
7 actions since 2023-09-29. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-04-06 | P00006 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO CHANGE THE COR. |
| 2025-07-10 | P00005 | Administrative change | $0 | FUNDING SWAP MODIFICATION TO ADD AND DE-OBLIGATE FUNDS FOR THE SAME AMOUNT. THIS MODIFICATION RESULTS IN A ZERO NET GAIN AND IS ONLY FOR LINE OF ACCOUNTINGS CHANGES. |
| 2025-04-22 | P00004 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO CHANGE THE COR. |
| 2025-03-10 | P00003 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE. |
| 2025-03-03 | P00002 | Supplemental agreement (work within scope) | $21.4K | IN SCOPE MODIFICATION FOR WEAPONS CLEANING EYE WASH AND OPERATIONAL SINK, TOWEL AND SOAP DISPENSER, ALONG WITH A CANINE UTILITY OPERATIONAL SINK TOWEL & SOAP DISPENSER. |
| 2024-02-21 | P00001 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO CHANGE THE POP DATES DUE TO THE CONSTRUCTION NTP. |
| 2023-09-29 | 0 | $24.89M | PHASE TWO DESIGN/BUILD CONTRACT FOR THE NIAGARA FALLS BORDER PATROL STATION. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| SECURITY CAM / COMM INSTALLATIONS FOR PROJECT |
| 2023-10-19 | Larson Design Group, Inc | $454.0K | PROVIDE DESIGN SERVICES AS REQUIRED UNDER THIS CONTRACT INCLUDING. ARCHITECTURE, INTERIOR DESIGNS, GRAPHICS, STRUCTURAL, MECHANICAL, ELECTRICAL, PLUMBING, TELECOMMUNICATION, SECURITY, BLAST ANALYSIS, LIFE SAFETY,… |
| 2024-03-20 | Worldwide Structural Fabrication | $334.8K | DESIGN , FABRICATION AND INSTALLATION OF COMMUNICATION TOWER AND ICE BRIDGE PER CONTRACT |
| 2026-09-15 | BRC International Corporation | $136.1K | FOUR (4) ADDITIONAL CARD READERS, INCLUDING ALL ASSOCIATED CABLING, EQUIPMENT, CONDUIT, AND INSTALLATION AT THE FOLLOWING LOCATIONS: O DOOR 610.00B O DOOR 610.00C, O DOOR 610.00E, O DOOR 630.08, - FIVE (5) INTERCOM… |
| 2026-09-11 | Worldwide Communications Consultants, Inc | $45.6K | FOUNDATION & ANCHOR BOLT REPAIR- LABOR & MATERIALS TO REPLACE DAMAGED ANCHOR BOLTS - LABOR & MATERIALS TO REPAIR FOUNDATION - NY PROFESSIONAL ENGINEER STAMPED REPAIR DRAWINGS - ANCHOR BOLT SPACING TEMPLATE. |