BORDER INFRASTRUCTURE CONSTRUCTION
Up for re-bid: ends 2027-09-30. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
11 actions since 2023-09-28. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-01 | P00010 | Supplemental agreement (work within scope) | $1.59M | ADD CONSTRUCTION REQUIREMENTS |
| 2026-04-10 | P00009 | Supplemental agreement (work within scope) | $7.60M | ADDED WORK AND PERIOD OF PERFORMANCE TIME |
| 2026-01-06 | P00008 | Supplemental agreement (work within scope) | $27.18M | DESIGN AND CONSTRUCTION FOR ALL NEW SHELTERS WITHIN STARR AND HIDALGO COUNTIES AND SHALL INCLUDE INSTALLATION AND CONNECTION OF POWER TO AND WITHIN THE SHELTER, GROUNDING, LGDS EQUIPMENT/SERVERS, CAMERA FIBER, ETC.. |
| 2025-09-16 | P00007 | Supplemental agreement (work within scope) | $76.00M | ADD: THE DESIGN AND CONSTRUCTION OF 30-FOOT-TALL BOLLARD WITH INGROUND FOUNDATION AND SITE CIVIL WORK WITHIN U.S FISH AND WILDLIFE SERVICE (USFWS) LAND AND PROVIDE GFM TRANSPORT. |
| 2025-05-22 | P00006 | Supplemental agreement (work within scope) | -$3.04M | DESCOPE OF BARRIER MATERIALS AND CONSTRUCTION WORK FOR A PORTION OF STARR COUNTY SEGMENT 4, THE REMOVAL OF ALL MATERIAL AND CONSTRUCTION OF LINEAR GROUND DETECTION SYSTEM (LGDS) FOR PORTIONS OF HIDALGO COUNTY AND ADD A SHELTER TO SEGMENT H4. |
| 2025-03-31 | P00005 | Supplemental agreement (work within scope) | $5.10M | ADD TO BOLLARD BARRIER: DESIGN AND CONSTRUCTION OF POWER, CCTV FIBER/CONDUIT, LIGHT POLE/CAMERA INSTALLATION FOR HIDALGO COUNTY, TX. |
| 2025-03-04 | P00004 | Supplemental agreement (work within scope) | $9.24M | BOLLARD WALL MODIFICATION - CONSTRUCTION |
| 2024-09-29 | P00003 | Supplemental agreement (work within scope) | $34.76M | CONSTRUCT BARRIER WORK |
| 2024-08-09 | P00002 | Supplemental agreement (work within scope) | $1.13M | ADDED WORK WITHIN SCOPE |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2024-06-28 | P00001 | Supplemental agreement (work within scope) | $1.79M | REVISED MATERIALS LOCATIONS AND EXTENDED THE POP |
| 2023-09-28 | 0 | $228.92M | BORDER INFRASTRUCTURE CONSTRUCTION |