BULK STEEL FOR SOUTHWEST BORDER BARRIER CONSTRUCTION PROJECTS
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
5 actions since 2026-02-11. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-24 | P00004 | Option exercised | $547.35M | MODIFICATION TO EXERCISE OPTION PURSUANT TO FAR 52.217-6 FOR 200,000 TONS OF STEEL AND LOGISTICAL SUPPORT SERVICES. |
| 2026-05-08 | P00003 | Supplemental agreement (work within scope) | $0 | NO-COST MODIFICATION TO SPLIT CLIN INTO TWO SEPARATE LINES FOR BILLING PURPOSES. |
| 2026-04-30 | P00002 | Supplemental agreement (work within scope) | $22.39M | MODIFICATION TO INTRODUCE TIGHTER SQUARENESS TOLERANCES ON THE PLATE STEEL USED AS ANTI-CLIMB PLATE. |
| 2026-03-05 | P00001 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO INCORPORATE A WAGE DETERMINATION FOR A LOCATION UNKNOWN AT TIME OF ORIGINAL AWARD. |
| 2026-02-11 | 0 | $1.45B | BULK STEEL FOR SOUTHWEST BORDER BARRIER CONSTRUCTION PROJECTS |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗