70LGLY25FGLB00117↗
Big Top Manufacturing LLC received this contract from Fletc Glynco Procurement Office, Federal Law Enforcement Training Center: $779.7K obligated so far for prefabricated tower structures. Its period of performance ended 2026-06-30.
Key facts · data as of Nov 5, 2026
- Recipient
- Big Top Manufacturing LLC
- Awarding agency
- Federal Law Enforcement Training Center (Department of Homeland Security)
- Contracting office
- Fletc Glynco Procurement Office (70LGLY)
- Obligated to date
- $779.7K
- Potential value
- $779.7K
- Ends
- 2026-06-30
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 5, 2026.
Cite this page: SpendQuery, Award 70LGLY25FGLB00117, data as of Nov 5, 2026, https://spendquery.com/award?id=CONT_AWD_70LGLY25FGLB00117_7015_GS07F073GA_4732
Big Top Manufacturing LLC: all federal awards · Department of Homeland Security: spending · Fletc Glynco Procurement Office: what it buys
PURCHASE OF A METAL FRAME STRUCTURE AND FABRIC COVER FOR EXISTING STRUCTURE FOR TRAINING VENUE AT GLYNCO, GA CAMPUS. THE METAL FRAME STRUCTURE WILL REPLACE A STRUCTURE THAT WAS DAMAGED DURING HURRICAN HELENE AND THE FABRIC COVER WILL REPLACE THE COVE
What it is
- Product or service
- Prefabricated Tower Structures (PSC 5445)
- Industry
- Prefabricated Metal Building and Component Manufacturing (NAICS 332311)
- Contracting office
- Fletc Glynco Procurement Office (70LGLY)
- Competition
- Full and open competition · 1 offer received
- Pricing
- Firm fixed price
- How it was bought
- GSA Schedule · under GS07F073GA
- Solicitation
- GSA EBUY 25VARIC02
- Where the work is
- Taylor, FL · district FL-02
- Funding law
- Other emergency or disaster supplementals
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
2 actions since 2025-08-29. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-22 | P00001 | Supplemental agreement (work within scope) | $0 | PURCHASE OF A METAL FRAME STRUCTURE AND FABRIC COVER FOR EXISTING STRUCTURE FOR TRAINING VENUE AT GLYNCO, GA CAMPUS. THE METAL FRAME STRUCTURE WILL REPLACE A STRUCTURE THAT WAS DAMAGED DURING HURRICAN HELENE AND THE FABRIC COVER WILL REPLACE THE COVE |
| 2025-08-29 | 0 | $779.7K | PURCHASE OF A METAL FRAME STRUCTURE AND FABRIC COVER FOR EXISTING STRUCTURE FOR TRAINING VENUE AT GLYNCO, GA CAMPUS. THE METAL FRAME STRUCTURE WILL REPLACE A STRUCTURE THAT WAS DAMAGED DURING HURRICAN HELENE AND THE FABRIC COVER WILL REPLACE THE COVE |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-05). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗