THIS IS A FIRM FIXED-PRICED TASK ORDER UNDER THE OASIS SB POOL 1 CONTRACT 47QRAD19D1001 FOR PROGRAM MANAGEMENT SUPPORT SERVICES TO SUPPORT VARIOUS PROGRAMS.
Up for re-bid: ends 2026-11-13. Recompete brief → · Justification for an Exception to Fair Opportunity ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
18 actions since 2024-07-19. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-29 | P00017 | Funding only | $8.7K | THE PURPOSE OF MODIFICATION P00017 TO CONTRACT 70Z02324F93220002 IS TO REMOVE HOURS FROM ONE POSITION FOR OPC AND ADD HOURS TO A NEW POSITION. |
| 2026-09-02 | P00016 | Funding only | $8.6K | THE PURPOSE OF MODIFICATION P00016 TO CONTRACT 70Z02324F93220002 IS TO REMOVE HOURS FROM ONE POSITION FOR HSC AND ADD HOURS TO ANOTHER POSITION. |
| 2026-07-14 | P00015 | Funding only | $32.0K | MODIFICATION P00015 REMOVES POSITION AND HOURS FROM ULC ACQUISITION SPECIALIST - SR BUSINESS AND FINANCIAL OPERATIONS SPECIALISTS, GROUP 2 AND ULC ACQUISITION SPECIALIST - SR-ENGINEER, GROUP 4 FROM THE REMAINDER OF OY1 AND SUBSEQUENT OPTION YEARS |
| 2026-06-26 | P00014 | Change order | $30.9K | REMOVE POSITION AND HOURS FROM JY-BUSINESS AND FINANCIAL OPERATIONS SPECIALISTS, GROUP 2, 13-2051 POSITION (POSITION 2024011). ADD POSITION ULC INTEGRATED MASTER SCHEDULE (IMS) SUPPORT POSITION, 3.1.6.14. ADD CAF AND CAF FUNDING. ADD FAR CLAUSE. |
| 2026-06-05 | P00013 | Funding only | $35.0K | THE PURPOSE OF MODIFICATION P00013 TO TASK ORDER 70Z02324F93220002 UNDER CONTRACT 47QRAD19D1001 IS TO ADD ADDITIONAL TRAVEL FUNDS TO OPTION YEAR 1 WCC TRAVEL CLIN 1008, IN THE AMOUNT OF $35,000.00. |
| 2026-06-03 | P00012 | Funding only | $64.0K | MODIFICATION P00012 IS TO CHANGE THE ALTERNATE COR, ADD FUNDING TO CLIN 1004 LABOR, AND ADD FUNDING TO1006 CAF. |
| 2026-02-26 | P00011 | Administrative change | $0 | THIS ADMINISTRATIVE MODIFICATION P00011 IS TO CHANGE THE ALTERNATE CONTRACTING OFFICER REPRESENTATIVE (ACOR) FROM SARAH MILLER TO LAURA SOUTHGATE EFFECTIVE IMMEDIATELY. |
| 2026-01-23 | P00010 | Administrative change | $0 | MODIFICATION P00010 IS AN ADMINISTRATIVE MODIFICATION TO CORRECT THE PERIOD OF PERFORMANCE DATE TIMES SO THAT INVOICES CAN BE PAID IN IPP. |
| 2026-01-15 | P00009 | Option exercised | $8.13M | MODIFICATION P00009 IS TO EXERCISE OPTION YEAR ONE CLNS. |
| 2025-12-09 | P00008 | Supplemental agreement (work within scope) | $813.1K | MODIFICATION P00008 IS TO ISSUE ANOTHER 30-DAY EXTENSION TO ALL BASE -YEAR CLINS. |
| 2025-11-12 | P00007 | Supplemental agreement (work within scope) | $813.1K | MODIFICATION P0007 IS TO ISSUE A 30-DAY EXTENSION TO ALL BASE -YEAR CLINS AND UPDATE THE OPTION TO EXTEND THE TERM OF THE CONTRACT CLAUSE. |
| 2025-09-24 | P00006 | Change order | $370.7K | THE PURPOSE OF THIS MOD P00006 IS TO ADD 6 POSITIONS FOR DOMICE LABOR AND FUNDS, TRAVEL FUNDS, AND CAF FUNDS. |
| 2025-08-06 | P00005 | Change order | $32.5K | ADD FUNDING FOR WCC LABOR, TRAVEL, AND CAF AND UPDATE THE COR FOR DOMICE TO SARAH MILLER ([email protected]) |
| 2025-05-29 | P00004 | Change order | $735.5K | THIS IS A MODIFICATION TO ADD, EXERCISE, AND REMOVE CLINS ON THE BASE PERIOD. |
| 2024-11-27 | P00003 | Supplemental agreement (work within scope) | $0 | MOD P00003 TO PROVIDE THE DD-254, ADD FAR CLAUSE 52.204-2, CHANGE THE KS AND KO, CHANGE THE TRANSITION PERIOD TIME, AND UPDATE THE POP OF THE CLINS |
| 2024-11-14 | P00002 | Supplemental agreement (work within scope) | $0 | FAR CLAUSE 52.242-15 'STOP-WORK ORDER' (AUG 1989) THE CONTRACTING OFFICER HEREBY RESCINDS THE 'STOP-WORK ORDER' ISSUED BY MODIFICATION P00001 AND UPDATED THE PERIOD OF PERFORMANCE. THE CONTRACTOR WILL START WORK ON THIS EFFORT. |
| 2024-08-15 | P00001 | Administrative change | $0 | FAR CLAUSE 52.242-15 'STOP-WORK ORDER' (AUG 1989) THE CONTRACTING OFFICER HEREBY ISSUES A 'STOP-WORK ORDER' ORDERING THE CONTRACTOR TO STOP WORK ON ALL PERFORMANCE UNDER THIS TASK ORDER. |
| 2024-07-19 | 0 | $6.99M | THIS IS A FIRM FIXED-PRICED TASK ORDER UNDER THE OASIS SB POOL 1 CONTRACT 47QRAD19D1001 FOR PROGRAM MANAGEMENT SUPPORT SERVICES TO SUPPORT VARIOUS PROGRAMS. |