70Z04721FPONCRO00↗

Rq-Aecom 2 JV received this contract from Fdcc(00047), U.S. Coast Guard: $3.59M obligated so far for construction of miscellaneous buildings. Its period of performance ended 2025-11-28.

Key facts · data as of Oct 25, 2026

Recipient
Rq-Aecom 2 JV
Awarding agency
U.S. Coast Guard (Department of Homeland Security)
Contracting office
Fdcc(00047) (70Z047)
Obligated to date
$3.59M
Potential value
$21.42M
Ends
2025-11-28

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 70Z04721FPONCRO00, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_70Z04721FPONCRO00_7008_70Z04718DRQAECM00_7008

REBUILD FACILITIES RESIDENT INSPECTION OFFICE (RIO) PONCE, PONCE, PUERTO RICO

Delivery Order · U.S. Coast Guard · to Rq-Aecom 2 JV (UEI NZCHS2HHXKT9) · data as of 2026-10-25

Obligated to date$3.59M15 actions
Current value$21.42Mwith options exercised
Period2021-06-22 → 2025-11-28current end date
Passed on$2.57Mto 17 subcontractors

What it is

Product or service
Construction of Miscellaneous Buildings (PSC Y1JZ)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
Fdcc(00047) (70Z047)
Competition
Full and open competition · 2 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 70Z04718DRQAECM00
Where the work is
Aguadilla, PR · district PR-98
Funding law
Other emergency or disaster supplementals

Obligations by fiscal year

FY2023$1.69M
FY2024$141.1K
FY2025$1.55M
FY2026$209.4K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

17 subawards totaling $2.57M (71.8% of what was obligated), as Rq-Aecom 2 JV reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.

SubcontractorAmountSubawardsWhereFirstLast
Alproem Engineering Contractors LLC$777.0K1PR2023-07-132023-07-13
King Business Interiors Inc$463.8K1OH2025-03-062025-03-06
Industrial Sprinkler Corp.$228.6K1PR2023-03-062023-03-06
Eas Systems Inc$212.7K1PR2023-01-262023-01-26
Rallypoint Group$179.1K1CA2022-11-232022-11-23
West Coast Energy Systems LLC$92.8K1CA2023-04-032023-04-03
Thermal Windows, Inc.$85.6K1OK2023-12-072023-12-07
Jax Fab Shop LLC$73.7K1FL2026-05-062026-05-06
CR Quality Roofing of PR, Inc$68.1K1PR2025-06-182025-06-18
Earth Engineers, Inc$66.0K1PR2023-11-062023-11-06
Duro-Last, Inc.$61.2K1MI2023-04-122023-04-12
Fire Control Corp$58.2K1PR2023-03-022023-03-02
Caribbean Wood PVM Working Corp$52.2K1PR2026-02-022026-02-02
Glasstra Group LLC$50.7K1PR2025-09-202025-09-20
Commissioning Team LLC$37.9K1IL2025-12-172025-12-17
Tomarco Contractor Specialties LLP$35.8K1CA2023-08-012023-08-01
Island Exterminating Services Inc$31.4K1PR2023-04-102023-04-10
The largest single subawards
DateToAmountFor
2023-07-13Alproem Engineering Contractors LLC$777.0KMECHANICAL & PLUMBING SYSTEM
2025-03-06King Business Interiors Inc$463.8KFF&E - OFFICE FURNITURE, A/V, FIRE EXTINGUISHERS
2023-03-06Industrial Sprinkler Corp.$228.6KFIRE SUPPRESSION SYSTEM
2023-01-26Eas Systems Inc$212.7KVIDEO SURVEILLANCE SYSTEM
2022-11-23Rallypoint Group$179.1KSUPPLY - DOORS, FRAMES & HARDWARE
2023-04-03West Coast Energy Systems LLC$92.8KGENERAC INDUSTRIAL DIESEL ENGINE DRIVEN GENERATOR SET
2023-12-07Thermal Windows, Inc.$85.6KWINDOWS
2026-05-06Jax Fab Shop LLC$73.7KALUMINUM RAILINGS MATERIAL
2025-06-18CR Quality Roofing of PR, Inc$68.1KDURO-LAST ROOFING SYSTEM
2023-11-06Earth Engineers, Inc$66.0KTESTING AND INSPECTION SERVICES
2023-04-12Duro-Last, Inc.$61.2KPVC ROOFING SYSTEM - MATERIALS
2023-03-02Fire Control Corp$58.2KFIRE ALARM & MASS NOTIFICATION SYSTEMS
2026-02-02Caribbean Wood PVM Working Corp$52.2KPLASTIC-LAMINATED-CLAD ARCHITECTURAL CABINETS & SOLID SURFACE
2025-09-20Glasstra Group LLC$50.7KINSTALLATION OF ALUMINUM-FRAMES STOREFRONT DOORS
2025-12-17Commissioning Team LLC$37.9KBUILDING COMMISSIONING
2023-08-01Tomarco Contractor Specialties LLP$35.8KSEISMIC RESTRAINTS & EQUIPMENT ANCHORAGE CALCULATIONS FOR MECHANICAL & PLUMBING SYSTEMS
2023-04-10Island Exterminating Services Inc$31.4KTERMITE CONTROL

Every action

15 actions since 2023-01-17. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-03-12P00020Supplemental agreement (work within scope)$209.4KP00020-THIS MODIFICATION IS BEING ISSUED TO PROVIDE ALL DESIGN, MATERIAL, LABOR, EQUIPMENT, AND SUPERVISION NECESSARY, ASSOCIATED WITH THE INSTALLATION AND CONNECTION OF THE NEW 150 KVA PAD MOUNTED TRANSFORMER.
2025-12-19P00019Supplemental agreement (work within scope)$0P00019-THIS MODIFICATION IS BEING ISSUED TO ACCESS LIQUIDATED DAMAGES IN THE AMOUNT OF $2,089.00 PER CALENDAR DAY.
2025-03-18P00018Supplemental agreement (work within scope)$519.5KP00018-THIS MODIFICATION IS BEING ISSUED TO AWARD THE REMAINING NEGOTIATED AMOUNT TO COMPLETELY COMPENSATE THE CONTRACTOR. SECTION 2.D OF IMPLEMENTING DEPARTMENT OF GOVERNMENT'S EFFICIENCY APPLIES TO THIS ACTION.
2025-03-05P00017Supplemental agreement (work within scope)$1.03MP00017-THIS MODIFICATION IS BEING ISSUED FOR ENVIRONMENTAL PERMITTING AND THE UNFORESEEN UNDERGROUND STORAGE TANK.
2024-12-18P00016Supplemental agreement (work within scope)$0P00016- BILATERAL MODIFICATION TO EXTEND THE CCD TO FEBRUARY 26, 2025 AT NO COST TO THE GOVERNMENT..
2024-09-04P00015Administrative change$0P00015- UNILATERAL MODIFICATION TO CHANGE THE COR TO LCDR JUAN FITZPATRICK.
2024-06-04P00014Administrative change$0P00014- UNILATERAL MODIFICATION TO CHANGE THE COR TO JOSHUA AGANON.
2024-04-15P00013Supplemental agreement (work within scope)$36.9KP00013- REA003/RQ PCO #10 UNFORESEEN CONTAMINATED SOILS AND WATER AT BOAT BAY..
2024-03-06P00012Supplemental agreement (work within scope)$9.8KP00012- CMR005/RQ PCO #11 SUBSURFACE UTILITY SURVEY IAW PRASA REQUIREMENTS IN PR.
2024-03-04P00011Supplemental agreement (work within scope)$23.6KP00011- REA002/RQ PCO #09 UNFORESEEN ARCHEOLOGICAL BRICK PIPING DISCOVERY
2024-01-30P00010Supplemental agreement (work within scope)$70.8KP00010- REA001 DESIGN AND PROCUEMENT AND INSTALLATION OF A 150KVA PAD MOUNTED TRANSFORMER.
2023-09-29P00009Supplemental agreement (work within scope)$642.8KP00009- REMOVAL OF UNFORESEEN UNDERGROUND STORAGE TANK.
2023-04-25P00008Supplemental agreement (work within scope)$11.8KP00008- UNFORESEEN UNDERGROUND STORAGE TANK.
2023-04-10P00006Supplemental agreement (work within scope)$0P00006 - ENVIRONMENTAL PERMIT DELAYS
2023-01-17P00005Supplemental agreement (work within scope)$1.03MP00005 - CORRECT FINAL DESIGN PACKAGE