- Obligated to date
- $2.52M
- Potential value
- $28.83M
- Ends
- 2024-05-03
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.
Cite this page: SpendQuery, Award 70Z04721FTYBEDB00, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_70Z04721FTYBEDB00_7008_70Z04718DWHITUR00_7008
Whiting-Turner Contracting Company, the: all federal awards · Department of Homeland Security: spending · Fdcc(00047): what it buys
REBUILD THE STA/ANT TYBEE FACILITIES AND WATERFRONT SHORELINE AT COCKSPUR ISLAND, GA.
What it is
- Product or service
- Construction of Miscellaneous Buildings (PSC Y1JZ)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Fdcc(00047) (70Z047)
- Competition
- Full and open competition · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 70Z04718DWHITUR00
- Solicitation
- 70Z04720RTYBEDB
- Where the work is
- Chatham, GA · district GA-01
- Funding law
- Other emergency or disaster supplementals
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
16 actions since 2022-12-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-19 | P00020 | Close-out | $0 | P00020- THIS MODIFICATION IS BEING ISSUED TO CLOSE OUT THE CONTRACT. |
| 2024-09-16 | P00019 | Supplemental agreement (work within scope) | $31.9K | P00019- ISSUED FOR CMR015R1 FOR GENERATOR ELECTRICAL HOOKUP FOR SEPTIC SYSTEM. |
| 2024-09-04 | P00018 | Supplemental agreement (work within scope) | $84.2K | P00018- ISSUED FOR REA005 FOR MISC AND ADDED CONTRACTOR COSTS, AND CMR016 FOR THE REPAIR OF A WIND DAMAGED HURRICANE RATED DOOR FRAME. |
| 2024-05-14 | P00017 | Supplemental agreement (work within scope) | $124.3K | P00017- ISSUED FOR THE AGREED TO COMPENSABLE COSTS FOR GENERAL CONDITIONS ON REA004 DUE TO NPS DELAYS. |
| 2024-03-26 | P00016 | Supplemental agreement (work within scope) | $20.1K | P00016- ISSUED FOR THE AGREED TO COMPENSABLE COSTS FOR GENERAL CONDITIONS ON CMR014 DUE TO 100 CALENDAR DAY CONTRACT EXTENSION. |
| 2024-03-12 | P00015 | Supplemental agreement (work within scope) | $126.6K | P00015- ISSUED FOR THE AGREED TO COMPENSABLE COSTS FOR GENERAL CONDITIONS ON CMR013 DUE TO 100 CALENDAR DAY CONTRACT EXTENSION. |
| 2023-09-11 | P00014 | Supplemental agreement (work within scope) | $0 | P00014- MODIFICATION ISSUED AS A NO COST MOD TO EXTEND THE CCD TO FEBRUARY 29, 2024. |
| 2023-09-11 | P00013 | Supplemental agreement (work within scope) | $64.3K | P00013- MODIFICATION ISSUED TO ADDRESS REA003 AND COSTS INVOLVED WITH DIFFERING SITE CONDITIONS ENCOUNTERED WITH GENERATOR PLATFORM. |
| 2023-09-11 | P00012 | Funding only | $329.1K | P00012- ISSUED AS A BILATERAL MODIFICATION TO ADDRESS CMR011, ADDITIONAL COMPENSABLE COSTS TO THE COTRACTOR DUE TO SCHEDULE DELAYS WHICH RESULTED IN ADDTIONAL GENERAL CONDITIONS. |
| 2023-08-21 | P00011 | Supplemental agreement (work within scope) | $432.4K | P00011- ISSUED FOR THE AGREED TO COMPENSABLE COSTS FOR GENERAL CONDITIONS ON CMR010 DUE TO PERMITTING AND NPS ISSUES RESULTING IN DELAYS. |
| 2023-07-19 | P00010 | Supplemental agreement (work within scope) | $890.7K | P00010- ISSUED AS A BILATERAL MODIFICATION TO ADDRESS CMR008, ASBESTOS REMOVAL, INSTALLATION OF FLAGPOLE AND INSTALLATION OF FORKLIFT CONCRETE SLAB. |
| 2023-06-07 | P00009 | Supplemental agreement (work within scope) | -$37.9K | P00009- ISSUED AS A BILATERAL MODIFICATION TO ADDRESS CREDIT DUE ON CMR007, RENOVATE ON EXISTING PUMP HOUSE WITH A CHANGE IN SCOPE ALONG WITH A 96 CALENDAR CONTRACT EXTENSION TO AUGUST 22, 2023. |
| 2023-02-02 | P00008 | Funding only | $223.8K | P00008- ISSUED AS A UNILATERAL MODIFICATION TO ADDRESS UPDATES NECESSARY TO COMPLETE THE OBLIGATION OF FUNDS ON P00007 WHICH COULD NOT BE COMPLETED IN THE FSMS SYSTEM. |
| 2023-01-08 | P00006 | Supplemental agreement (work within scope) | $41.6K | P00006 - CMR003 PUMP HOUSE DESIGN FEES. |
| 2023-01-08 | P00005 | Supplemental agreement (work within scope) | $193.1K | P00005 - REA002 FOR TIME AND COST IMPACTS DUE TO NPS ACTIONS AFFECTING GENERAL CONDITIONS AND THE SCHEDULE. |
| 2022-12-13 | P00007 | Supplemental agreement (work within scope) | $0 | P00007 - CMR004 FOR DESIGN SERVICES AND WATERLINE REPLACEMENT FOR THE DB PROJECT, USCG TYBEE, COCKSPUR ISLAND, GA. FUNDING REMOVED AND PLACED ON P00008 TO DUE FSMS ISSUES. |