70Z04722F43000008↗
Whiting-Turner Contracting Company, the received this contract from Fdcc(00047), U.S. Coast Guard: $14.22M obligated so far for construction of miscellaneous buildings. It runs to 2026-12-31.
Key facts · data as of Oct 25, 2026
- Recipient
- Whiting-Turner Contracting Company, the
- Awarding agency
- U.S. Coast Guard (Department of Homeland Security)
- Contracting office
- Fdcc(00047) (70Z047)
- Obligated to date
- $14.22M
- Potential value
- $49.00M
- Ends
- 2026-12-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award 70Z04722F43000008, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_70Z04722F43000008_7008_70Z04718DWHITUR00_7008
Whiting-Turner Contracting Company, the: all federal awards · Department of Homeland Security: spending · Fdcc(00047): what it buys · The follow-on: recompete brief
DESIGN/BUILD PROJECT AT USCG YARD, CURTIS BAY MD, INCLUDES DEMOLITION OF 2 BUILDINGS, WATERFRONT WORK, CONSTRUCTION OF 2 BAY MAINTENANCE BUILDINGS, SITE WORK AND CONSTRUCT TRAVEL PLATFORM.
Up for re-bid: ends 2026-12-31. Recompete brief →
What it is
- Product or service
- Construction of Miscellaneous Buildings (PSC Y1JZ)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Fdcc(00047) (70Z047)
- Competition
- Full and open competition · 1 offer received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 70Z04718DWHITUR00
- Solicitation
- 70Z04722RCGRADP00
- Where the work is
- Anne Arundel, MD · district MD-03
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
10 actions since 2023-07-06. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-09 | P00010 | Supplemental agreement (work within scope) | $1.49M | MODIFICATION P00010 IS ISSUED TO ADD FUNDING FOR ADDITIONAL DESIGN, PERMIT REVISIONS, SITE INVESTIGATION, AND ENVIRONMENTAL ASSESSMENT AS A RESULT OF DIFFERING SITE CONDITIONS. FRC, RECURRING DEPOT AVAILABILITY PROGRAM AT USCG YARD, CURTIS BAY, MD |
| 2026-06-04 | P00009 | Supplemental agreement (work within scope) | $248.5K | MODIFICATION P00009 IS ISSUED TO ADD FUNDING FOR ADDITIONAL DESIGN, PERMIT REVISIONS, SITE INVESTIGATION, AND ENVIRONMENTAL ASSESSMENT AS A RESULT OF DIFFERING SITE CONDITIONS. FRC, RECURRING DEPOT AVAILABILITY PROGRAM AT USCG YARD, CURTIS BAY, MD |
| 2026-04-02 | P00008 | Supplemental agreement (work within scope) | $419.4K | MODIFICATION P00008 IS ISSUED TO ADD FUNDING FOR COMPENSABLE 30 DAY TIME IMPACT AS A RESULT OF DIFFERING SITE CONDITIONS ON P00007. |
| 2025-09-29 | P00007 | Supplemental agreement (work within scope) | $4.33M | MODIFICATION P00007 IS ISSUED TO ADDRESS DIFFERING SITE CONDITIONS. |
| 2025-06-25 | P00006 | Supplemental agreement (work within scope) | $280.4K | MODIFICATION P00006 IS ISSUED TO ADDRESS RELOCATION OF EXISTING UNDERGROUND ELECTRICAL CONDUIT/PROPOSED TELECOM CHANGES & ADDITIONAL WORK. |
| 2024-12-11 | P00005 | Supplemental agreement (work within scope) | $0 | MODIFICATION P00005 IS ISSUED TO ADDRESS NO-COST CHANGE TO SPECIFICATIONS WITH USAGE OF STEEL PIPE VERSUS COPPER PIPE AND THE CHANGE IN COLOR OF THE TAPE TO IDENTIFY COMPRESSED AIR SYSTEM. |
| 2024-06-26 | P00004 | Supplemental agreement (work within scope) | $3.52M | MODIFICATION P00004 IS ISSUED TO ADDRESS WHARF/BULKHEAD REDESIGN IN CMR002A AND CMR002B COMBINED. |
| 2024-06-04 | P00003 | Administrative change | $0 | MODIFICATION P00003 IS ISSUED TO CHANGE THE COR TO LAWRENCE WHITE FOR INVOICING PURPOSES IN IPP.GOV. |
| 2023-07-12 | P00002 | Administrative change | $0 | MODIFICATION P00002 IS ISSUED AS A UNILATERAL MODIFICATION TO INCORPORATE FAR 52.222-55 EXECUTIVE ORDER 14026. |
| 2023-07-06 | P00001 | Supplemental agreement (work within scope) | $3.93M | MODIFICATION P00001 IS ISSUED TO ADDRESS DIFFERING SITE CONDITIONS ADDRESSED IN CMR001. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗