DRY-DOCK: USCGC RELIANCE FY25 DDS PERIOD OF PERFORMANCE (POP): 20 AUGUST 2025 - 28 OCTOBER 2025
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
26 actions since 2025-08-08. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-04-10 | P00025 | Change order | $3.9K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-071: CONTRACT EXTENSION TO 4/17/26 |
| 2026-04-09 | P00024 | Supplemental agreement (work within scope) | $17.1K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-070: CONTRACT EXTENSION TO 4/6/26 |
| 2026-04-02 | P00023 | Supplemental agreement (work within scope) | $27.2K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-067: COMPENSATE KTR FOR 4-DAY EXTENSION FOR PIER SERVICES |
| 2026-03-30 | P00022 | Supplemental agreement (work within scope) | $92.6K | INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-50 PORT SHAFT & HUB ALIGNMENT CR-60 WELDING OF FAIRWATERS ONTO STERN TUBE CR-63 MODIFY STBD MRG TO GFM COUPLING CR-64 REPAIR MISALIGNMENT OF PORT AND STBD SHAFT SEAL CR-65 5-DAY NO COST CONTRACT EXTENSION |
| 2026-03-27 | P00021 | Supplemental agreement (work within scope) | $75.0K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-061: COMPENSATE KTR FOR ADDITIONAL INDUCTION HEATER TO HEAT COUPLING ADEQUATELY TO 750 DEGREES |
| 2026-03-12 | P00020 | Supplemental agreement (work within scope) | $99.5K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-062: 10 DAY EXTENSION TO COMPLETE WATERBORNE PORTION OF WORK ITEM 10. PERIOD OF PERFORMANCE HAS BEEN EXTENDED BY TEN (10) DAYS TO 23 MARCH 2026. |
| 2026-03-04 | P00019 | Supplemental agreement (work within scope) | $13.0K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-055: COMPENSATE KTR TO REPAIR DAMAGED SUPERSTRUCTURE, ELECTRICAL INTERFERENCE FOUNDATIONS, STUFFING TUBES AND CABLE |
| 2026-03-03 | P00018 | Supplemental agreement (work within scope) | $97.0K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-058: CR TO FOLLOW TO COMPENSATE KTR FOR LABOR AND MATERIALS TO CROP AND RENEW THE APPROXIMATELY 25 LINEAR FOOT SECTION OF DAMAGED POTABLE WATER PIPING |
| 2026-02-26 | P00017 | Supplemental agreement (work within scope) | $96.8K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-051: DAMAGED OVERHEAD PLATING IN FOREPEAK (4-FP-0-W) CR-052: DAMAGED OVERHEAD PLATING IN (4-172-2-W) CR-053: DAMAGED OVERHEAD PLATING (4-164-2-J) |
| 2026-02-20 | P00016 | Supplemental agreement (work within scope) | $14.2K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-054: COMPENSATE KTR TO PERFORM A LASER DIMENSIONAL INSPECTION TO ALIGN SHAFT TO THE HUB CR-059: COMPENSATE KTR FOR TIME AND LABOR TO ALIGN NEW HUB ASSEMBLY TO THE SHAFT |
| 2026-02-10 | P00015 | Supplemental agreement (work within scope) | $8.8K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-049: HUB ATTACHMENT BOLTS |
| 2026-02-04 | P00014 | Supplemental agreement (work within scope) | $35.0K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-046: DUPLEX STRAINER INSTALLATION CR-048: STBD RUDDER BEARING |
| 2026-01-16 | P00013 | Supplemental agreement (work within scope) | $1.49M | INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-029: POTABLE WATER TANKS, REPAIR CR-038: SUPERSTRUCTURE REPAIRS CR-045: SHAFT ALIGNMENT PERIOD OF PERFORMANCE EXTENDED TO 13 MARCH 2026. |
| 2025-12-31 | P00012 | Supplemental agreement (work within scope) | $43.5K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-043: JP-5 FUEL FILTER/SEPARATOR FOUNDATIONS CR-044: PORT AND STBD HUB DOWEL PINS |
| 2025-12-23 | P00011 | Supplemental agreement (work within scope) | $86.9K | MODIFICATION TO INCORPORATE FOLLOWING CHANGE REQUESTS: CR-039: DUPLEX STRAINER FOUNDATIONS REPAIR CR-040: HUB ATTACHMENT BOLTS, FABRICATE CR-042: FIRE PUMP #2 FOUNDATION |
| 2025-12-19 | P00010 | Supplemental agreement (work within scope) | $98.0K | MODIFICATION TO INCORPORATE FOLLOWING CHANGE REQUESTS: CR-028: PORT HUB, RENEW AND OD BOX, REPAIR CR-037: DUPLEX STRAINERS, REPAIR |
| 2025-12-08 | P00009 | Supplemental agreement (work within scope) | $242.5K | INCORPORATE FOLLOWING CHANGE REQUESTS: 19:FOREPEAK TANK REPAIR 20:FREEBOARD CROP & RENEW 25:MSD TANK TOP REPAIR 26:STRAINER FOUNDATIONS 30:DAMAGED OVERHEAD PLATE 31:MANHOLE COVER LIDS MSD 33:UT SHELL DESCOPE 34:MAST SUBSTRATE INSPECT 35:DESCOPE WI13 |
| 2025-12-02 | P00008 | Supplemental agreement (work within scope) | $91.5K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-013: CPP RELIEF VALVES CR-018: PORT AND STARBOARD SHAFT CHANGE OUT |
| 2025-12-02 | P00007 | Supplemental agreement (work within scope) | $91.9K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-036: DUPLEX STRAINERS, PROCURE |
| 2025-11-21 | P00006 | Supplemental agreement (work within scope) | $62.3K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-011: DOPPLER SPEED LOG CABLE CR-012: CPP REPAIRS CR-017: ACTIVATE WORK ITEM 14 CR-032: VALVE 4-112-1, RENEW FLANGE |
| 2025-11-18 | P00005 | Supplemental agreement (work within scope) | $2.51M | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-021: HULL RENEWAL CR-022: CONTRACT EXTENSION CR-027: DRYDOCK EXTENSION 05NOV25-11NOV25 PERIOD OF PERFORMANCE HAS BEEN EXTENDED TO 17 JANUARY 2026. |
| 2025-11-12 | P00004 | Supplemental agreement (work within scope) | $157.7K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-015: ACTIVATE WORK ITEM 46 CR-024: VALVE, RENEW CR-027: DRYDOCK EXTENSION 05NOV25-11NOV25 PERIOD OF PERFORMANCE HAS BEEN EXTENDED BY SEVEN (7) DAYS TO 11 NOVEMBER 2025. |
| 2025-10-29 | P00003 | Supplemental agreement (work within scope) | $74.4K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-004: SEA VALVE OVERHAUL/RENEWAL CR-014: WASTER PIECES, RENEW CR-016: 2 1/2-INCH CHECK VALVE, OVERHAUL CR-023: DRYDOCK EXTENSION PERIOD OF PERFORMANCE EXTENDED BY 7-DAYS TO 4 NOVEMBER 2025 |
| 2025-10-21 | P00002 | Supplemental agreement (work within scope) | $58.1K | MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-005:SEA VALVE FLANGES, RENEW CR-006:4-174-1-W TLI CABLE CR-007:RENEW AFT AND INTERMEDIATE BEARINGS CR-008:PORT OIL TUBE, REPAIR CR-009:RUDDER, REPAIR CR-010:JP-5 ADDITIONAL FUEL REMOVAL |
| 2025-09-30 | P00001 | Supplemental agreement (work within scope) | $34.6K | DRY-DOCK: USCGC RELIANCE FY25 DDS MODIFICATION TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-001: PARTIAL DESCOPE WILDCAT RENEWAL CR-002: COUPLING MOUNTING KIT RENTAL - KIT TMHK 38R SKF CR-003: SHAFT SEAL BULLKHEAD MOUNTING FLANGE BELZONA REPAIR |
| 2025-08-08 | 0 | $3.40M | DRY-DOCK: USCGC RELIANCE FY25 DDS PERIOD OF PERFORMANCE (POP): 20 AUGUST 2025 - 28 OCTOBER 2025 |