70Z08026CMECP0016↗

Colonna'S Ship Yard, Incorporated received this contract from SFLC Procurement Branch 1(00080), U.S. Coast Guard: $7.69M obligated so far for non-nuclear ship repair (east). Its period of performance ended 2026-09-15.

Key facts · data as of Oct 22, 2026

Recipient
Colonna'S Ship Yard, Incorporated
Awarding agency
U.S. Coast Guard (Department of Homeland Security)
Contracting office
SFLC Procurement Branch 1(00080) (70Z080)
Obligated to date
$7.69M
Potential value
$7.69M
Ends
2026-09-15

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.

Cite this page: SpendQuery, Award 70Z08026CMECP0016, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_70Z08026CMECP0016_7008_-NONE-_-NONE-

DRY-DOCK: USCGC THETIS DDL FY26 PERIOD OF PERFORMANCE: 15 JUNE 2026 - 12 SEPTEMBER 2026

Definitive Contract · U.S. Coast Guard · to Colonna'S Ship Yard, Incorporated (UEI JSAXGRLNEJ63) · data as of 2026-10-22

Obligated to date$7.69M11 actions
Current value$7.69Mwith options exercised
Period2026-06-15 → 2026-09-15current end date

Up for re-bid: ends 2026-09-15. Recompete brief → · USCGC CROCODILE DD2 FY27 #1 MDE W5 ↗

What it is

Product or service
Non-Nuclear Ship Repair (East) (PSC J998)
Industry
Ship Building and Repairing (NAICS 336611)
Contracting office
SFLC Procurement Branch 1(00080) (70Z080)
Competition
Competed under simplified acquisition · 2 offers received
Set-aside
Small business
Pricing
Firm fixed price
How it was bought
Standalone contract
Solicitation
70Z08026QMECP0007
Where the work is
Norfolk City, VA · district VA-03

Obligations by fiscal year

FY2026$7.69M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

11 actions since 2026-05-15. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-29P00010Supplemental agreement (work within scope)$116.9KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-003: SEA VALVES CR-004: ANCHOR WINDLASS SHIPPING STANDS CR-010: ENGINE ROOM FAN CONTROLLERS, RENEW CR-012: CONTROLLABLE PITCH PROPELLER, HUB INSPECTION
2026-09-22P00009Supplemental agreement (work within scope)$171.7KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-003: SEA VALVES CR-004: ANCHOR WINDLASS SHIPPING STANDS CR-010: ENGINE ROOM FAN CONTROLLERS, RENEW CR-012: CONTROLLABLE PITCH PROPELLER, HUB INSPECTION
2026-09-16P00008Supplemental agreement (work within scope)$160.6KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-003: SEA VALVES CR-004: ANCHOR WINDLASS SHIPPING STANDS CR-010: ENGINE ROOM FAN CONTROLLERS, RENEW CR-012: CONTROLLABLE PITCH PROPELLER, HUB INSPECTION
2026-08-27P00007Supplemental agreement (work within scope)$154.9KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-003: SEA VALVES CR-004: ANCHOR WINDLASS SHIPPING STANDS CR-010: ENGINE ROOM FAN CONTROLLERS, RENEW CR-012: CONTROLLABLE PITCH PROPELLER, HUB INSPECTION
2026-08-26P00006Supplemental agreement (work within scope)$456.4KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-003: SEA VALVES CR-004: ANCHOR WINDLASS SHIPPING STANDS CR-010: ENGINE ROOM FAN CONTROLLERS, RENEW CR-012: CONTROLLABLE PITCH PROPELLER, HUB INSPECTION
2026-08-11P00005Supplemental agreement (work within scope)$606.9KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-003: SEA VALVES CR-004: ANCHOR WINDLASS SHIPPING STANDS CR-010: ENGINE ROOM FAN CONTROLLERS, RENEW CR-012: CONTROLLABLE PITCH PROPELLER, HUB INSPECTION
2026-07-21P00004Supplemental agreement (work within scope)$156.0KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-003: SEA VALVES CR-004: ANCHOR WINDLASS SHIPPING STANDS CR-010: ENGINE ROOM FAN CONTROLLERS, RENEW CR-012: CONTROLLABLE PITCH PROPELLER, HUB INSPECTION
2026-07-10P00003Supplemental agreement (work within scope)$8.6KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUESTS: CR-005: SHAFT FAIRWATERS AND ROPE GUARDS, VISUAL INSPECTION CR-007: APPENDAGES (U/W), PRESERVE (INTERNAL) AND LEAK TEST CR-008: VOID LEAK TEST
2026-07-07P00002Supplemental agreement (work within scope)$38.3KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-002 - ACTIVATE WORK ITEM 14
2026-06-26P00001Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FOLLOWING CHANGE REQUEST: CR-001: INCLEMENT WEATHER - DRY DOCKING PERIOD OF PERFORMANCE HAS BEEN EXTENDED BY THREE (3) DAYS TO 15 SEPTEMBER 2026.
2026-05-150$5.82MDRY-DOCK: USCGC THETIS DDL FY26 PERIOD OF PERFORMANCE: 15 JUNE 2026 - 12 SEPTEMBER 2026

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗