Inland Construction & Engineering Inc received this contract from Ceu Miami(00082), U.S. Coast Guard: $481.7K obligated so far for repair or alteration of other non-building facilities. Its period of performance ended 2026-09-30.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 70Z08222FABCD0024, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_70Z08222FABCD0024_7008_70Z08219DPMV11600_7008
Inland Construction & Engineering Inc: all federal awards · Department of Homeland Security: spending · Ceu Miami(00082): what it buys · The follow-on: recompete brief
CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, TOOLS, MATERIALS AND SUPERVISION FOR REPAIR WHARF (BENTS 42 THRU 55) AT CORPUS CHRISTI, TX.
Up for re-bid: ends 2026-09-30. Recompete brief → · Repair Punta Borinquen Lighthouse at USCG Base Borinquen, Aguadilla, Puerto Rico (PNUM 2993811) ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2023-08-04. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-27 | P00004 | Administrative change | $0 | THIS NO COST TIME MODIFICATION IS ISSUED TO ALLOW ADDITIONAL TIME TO PROCESS THE FINAL INVOICE IN THE AMOUNT OF $5,000. CCD UPDATED TO 30 SEPT 2026. |
| 2026-07-09 | P00003 | Administrative change | $0 | MODIFICATION REASON: TIME EXTENSION AND COR UPDATE COR UPDATED TO ADRIAN BRITO; CCD CHANGED TO 18 JUL 2026; CONTRACT VALUE REMAINS UNCHANGED |
| 2023-09-26 | P00002 | Supplemental agreement (work within scope) | $41.0K | MOD TO COMPLETE ALL PIER PILE REPAIRS AND ALL PIER REPAIRS ENCLOSED IN THE APPROVED FINAL DESIGN AND IN ACCORDANCE WITH THE PROJECT SPECIFICATIONS. CCD OF 4/24/24 REMAINS UNCHANGED. NET INCREASE: $41,027.07 NEW TOTAL: $3,129,242.18 |
| 2023-08-04 | P00001 | Supplemental agreement (work within scope) | $440.7K | REPAIR WATERFRONT HARFAC AT USCG SECTOR CORPUS CHRISTI, TX |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗