70Z08321FPCR00100↗

Syncon LLC received this contract from Ceu Cleveland(00083), U.S. Coast Guard: $853.4K obligated so far for repair or alteration of miscellaneous buildings. Its period of performance ended 2024-02-09.

Key facts · data as of Oct 25, 2026

Recipient
Syncon LLC
Awarding agency
U.S. Coast Guard (Department of Homeland Security)
Contracting office
Ceu Cleveland(00083) (70Z083)
Obligated to date
$853.4K
Potential value
$1.53M
Ends
2024-02-09

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 70Z08321FPCR00100, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_70Z08321FPCR00100_7008_70Z08318DPCR07700_7008

P/N 6052879, REPLACE FIRE SUPPRESSION SYSTEM AND FIRE ALARMS IN BUILDING #77 AT CG BASE ELIZABETH CITY, ELIZABETH CITY, NC

Delivery Order · U.S. Coast Guard · to Syncon LLC (UEI VCASGYK6ADM4) · data as of 2026-10-25

Obligated to date$853.4K3 actions
Current value$1.53Mwith options exercised
Period2021-03-04 → 2024-02-09current end date

What it is

Product or service
Repair or Alteration of Miscellaneous Buildings (PSC Z2JZ)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
Ceu Cleveland(00083) (70Z083)
Competition
Full and open after exclusion of sources · 3 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 70Z08318DPCR07700
Where the work is
Pasquotank, NC · district NC-01

Obligations by fiscal year

FY2023$466.4K
FY2024$387.0K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

3 actions since 2023-03-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2023-12-26P00004Supplemental agreement (work within scope)$387.0KREPLACE SPRINKLER PIPING AND SPRINKLER HEADS FOR EXISTING DELUGE SYSTEM IN HANGER 77. THIS INCLUDES ROOM 111 (BLASTING AREA) AND ROOM 118 (HOPPER ROOM). REHABILITATE ROOM 114 (EXHAUST AIR PLENUM) TO FUNCTION AS SEPARATE DELUGE SYSTEM
2023-09-08P00003Supplemental agreement (work within scope)$0TIME EXTENSION TO 12/01/2023
2023-03-30P00002Supplemental agreement (work within scope)$466.4KDIFFERING SITE CONDITIONS, BASE WORK CANNOT BE COMPLETED WITHOUT THIS ADDITIONAL WORK.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗