70Z08823FOAKL0004↗
Sustainable Group/Terraphase Engineering JV LLC received this contract from Ceu Oakland(00088), U.S. Coast Guard: $2.45M obligated so far for maintenance of office buildings. Its period of performance ended 2025-11-28.
Key facts · data as of Oct 25, 2026
- Recipient
- Sustainable Group/Terraphase Engineering JV LLC
- Awarding agency
- U.S. Coast Guard (Department of Homeland Security)
- Contracting office
- Ceu Oakland(00088) (70Z088)
- Obligated to date
- $2.45M
- Potential value
- $2.45M
- Ends
- 2025-11-28
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award 70Z08823FOAKL0004, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_70Z08823FOAKL0004_7008_70Z08818DPQQ21300_7008
Sustainable Group/Terraphase Engineering JV LLC: all federal awards · Department of Homeland Security: spending · Ceu Oakland(00088): what it buys
CASREP: AMEND - REPLACE ROOFS AND REPAIR EXTERIOR AT STATION BODEGA BAY, CA AND DEMOLISH GASOLINE FUELING SYSTEM AT STATION BODEGA BAY, CA.
What it is
- Product or service
- Maintenance of Office Buildings (PSC Z1AA)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Ceu Oakland(00088) (70Z088)
- Competition
- Full and open after exclusion of sources · 3 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 70Z08818DPQQ21300
- Where the work is
- Sonoma, CA · district CA-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
6 actions since 2023-04-18. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-12-16 | P00005 | Administrative change | $64.8K | CASREP: AMEND - REPLACE ROOFS AND REPAIR EXTERIOR AT STATION BODEGA BAY, CA AND DEMOLISH GASOLINE FUELING SYSTEM AT STATION BODEGA BAY, CA. |
| 2025-11-10 | P00004 | Supplemental agreement (work within scope) | $0 | CASREP: AMEND - REPLACE ROOFS AND REPAIR EXTERIOR AT STATION BODEGA BAY, CA AND DEMOLISH GASOLINE FUELING SYSTEM AT STATION BODEGA BAY, CA. |
| 2025-06-27 | P00003 | Supplemental agreement (work within scope) | $24.1K | CASREP: AMEND - REPLACE ROOFS AND REPAIR EXTERIOR AT STATION BODEGA BAY, CA AND DEMOLISH GASOLINE FUELING SYSTEM AT STATION BODEGA BAY, CA. |
| 2025-06-23 | P00002 | Supplemental agreement (work within scope) | $138.6K | CASREP: AMEND - REPLACE ROOFS AND REPAIR EXTERIOR AT STATION BODEGA BAY, CA AND DEMOLISH GASOLINE FUELING SYSTEM AT STATION BODEGA BAY, CA. |
| 2025-01-06 | P00001 | Additional work (new agreement) | $57.5K | CASREP: AMEND - REPLACE ROOFS AND REPAIR EXTERIOR AT STATION BODEGA BAY, CA AND DEMOLISH GASOLINE FUELING SYSTEM AT STATION BODEGA BAY, CA. |
| 2023-04-18 | 0 | $2.17M | CASREP: AMEND - REPLACE ROOFS AND REPAIR EXTERIOR AT STATION BODEGA BAY, CA AND DEMOLISH GASOLINE FUELING SYSTEM AT STATION BODEGA BAY, CA. |