THE PURPOSE OF THIS CONTRACT IS TO PROVIDE COMPLETION OF THE ALREADY EXISTING 90% ENGINEERING DESIGNS, PERFORM VALUE ENGINEERING, AND PROVIDE CONSTRUCTION SERVICES AS DESCRIBED IN DETAIL IN SECTION C, STATEMENT OF WORK FOR THE USAID/SOUTH SUDAN JUBA
Up for re-bid: ends 2026-12-31. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
11 actions since 2023-09-29. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-03 | P00010 | Administrative change | $161.8K | MODIFICATION TO ADMINISTRATIVELY MOVE FUNDING FROM USAID TO STATE SYSTEMS FOR CONTINUED SUPPORT OF SERVICING AND MANAGEMENT OF USAID AWARD (19AQMM26C0993) |
| 2026-09-03 | P00009 | Transfer | -$161.8K | THE PURPOSE OF THIS CONTRACT IS TO PROVIDE COMPLETION OF THE ALREADY EXISTING 90% ENGINEERING DESIGNS, PERFORM VALUE ENGINEERING, AND PROVIDE CONSTRUCTION SERVICES AS DESCRIBED IN DETAIL IN SECTION C, STATEMENT OF WORK FOR THE USAID/SOUTH SUDAN JUBA |
| 2026-07-22 | P00008 | Supplemental agreement (work within scope) | $0 | NO COST EXTENSION TO ACCOUNT FOR EXCUSABLE DELAYS |
| 2026-06-03 | P00007 | Supplemental agreement (work within scope) | $0 | NO COST EXTENSION TO ACCOUNT FOR EXCUSABLE DELAYS |
| 2025-11-10 | P00006 | Supplemental agreement (work within scope) | $0 | NO COST EXTENSION TO ACCOUNT FOR EXCUSABLE DELYAYS |
| 2025-08-21 | P00005 | Administrative change | $0 | ENSURE COMPLIANCE WITH EXECUTIVE ORDERS (EO) 14173; 14168; 14148; AND 14208. |
| 2025-08-12 | P00004 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE CO/COR AND PROVIDE INVOICING INFORMATION |
| 2025-06-03 | P00003 | Additional work (new agreement) | $213.0K | USAID/SOUTH SUDAN JUBA RESIDENT COMPOUND KITCHEN RECONSTRUCTION (JUBA RCK) PROJECT |
| 2024-09-27 | P00002 | Administrative change | $0 | THIS ADMINISTRATIVE MODIFICATION EXTENDS THE CONTRACT'S END DATE IN THE GLAAS. |
| 2024-06-26 | P00001 | Administrative change | $0 | THIS ADMINISTRATIVE MODIFICATION EXTENDS THE END DATE OF THE CONTRACT IN THE GLAAS BY THREE (3) MONTHS FROM JUNE 26, 2024, TO SEPTEMBER 24, 2024. |
| 2023-09-29 | 0 | $644.7K | THE PURPOSE OF THIS CONTRACT IS TO PROVIDE COMPLETION OF THE ALREADY EXISTING 90% ENGINEERING DESIGNS, PERFORM VALUE ENGINEERING, AND PROVIDE CONSTRUCTION SERVICES AS DESCRIBED IN DETAIL IN SECTION C, STATEMENT OF WORK FOR THE USAID/SOUTH SUDAN JUBA |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗