TASK ORDER NO. 19 DESERT SAGE SOLAR PROJECT
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
7 actions since 2024-09-20. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-05-18 | P00006 | Funding only | $40.0K | P00006 FINALIZES ADD'L WORK ON CARPORTS NOT INCLUDED IN DESIGN FROM SUBCONTRACTOR TO THE GOV'T. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. |
| 2026-04-24 | P00005 | Funding only | $21.6K | P00005 DUE TO EV CHARGING STATIONS CONNECTOR'S BEING CHANGED FROM ORIGINAL SOW, THIS MOD WILL BE THE FINAL PRICING MOD TO CHANGE THOSE CONNECTOR'S AND PARKING STRIPS. THIS MODIFICATION IS FOR THE CONTRACTOR'S CHANGE ORDER REQUEST FOR P |
| 2025-12-03 | P00004 | Administrative change | $0 | P00004 UPDATES THE GOVERNMENT ACCEPTED FINAL SCHEDULE FOR PROJECT, SEE ATTACHED SCHEDULE FOR PROJECT. THIS IS A NO COST MOD. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. |
| 2025-11-13 | P00003 | Administrative change | $0 | P00003 THIS MODIFICATION IS A NO COST MODIFICATION TO CLARIFY THE CHANGES IN P00002 WHICH ADDED A SCOPE OF WORK CHANGE REQUIREMENT REQUIRING THE CONTRACTOR (CECIL AND CECIL) TO BECOME THE ENGINEER OF RECORD (EOR) USING A SUBCONTRACTOR SPECIALIZING IN |
| 2025-09-18 | P00002 | Change order | $311.5K | P00002 INCLUDES A NEW DESIGN/CONSTRUCT REVISED SOW FOR THE CARPORTS. NEW PERIOD OF PERFORMANCE FOR THIS CHANGE AND REQUEST FOR PRICING FOR THIS CHANGE. BRAND NAME IS JUSTIFIED FOR THIS PROJECT AND APPROVED BY CCO. ATTACHED IS THE REVISED QUOTE FOR P0 |
| 2024-12-23 | P00001 | Funding only | $17.0K | P00001 INCREASED AMOUNT FOR PANELS DUE TO COST FOR MADE IN AMERICA COMPLIANT INCREASES SINCE THE AWARD WAS MADE. SEE ATTACHMENT FOR THE INCREASE IN COSTS. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. |
| 2024-09-20 | 0 | $1.98M | TASK ORDER NO. 19 DESERT SAGE SOLAR PROJECT |