Putting the award page together from the records…
Putting the award page together from the records…
TASK ORDER FOR SACRED OAKS SOLAR PROJECT SEE PROJECT DETAILS IN THE ATTACHMENT CONTRACTOR'S PROPOSAL.
Up for re-bid: ends 2026-12-01. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
3 actions since 2024-09-24. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-05-28 | P00002 | Change order | $271.4K | P00002 REQUEST FOR QUOTE (RFQ) FOR THE REVISED SCOPE OF WORK (SOW) REQUIREMENTS AND THE NEW GEOTECH REPORT REQUIREMENTS, ATTACHMENT A REVISED SOW AND ATTACHMENT B UPDATED GEOTECH REPORT. PLEASE PROVIDE THE CONTRACTOR'S PRICING BREAKDOWN AND A FI |
| 2024-12-23 | P00001 | Funding only | $29.4K | P00001 INCREASES COST TO THE TO DUE TO PANELS MIA COST INCREASED SINCE AWARD. SEE ATTACHED QUOTE FOR COST DETAILS. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. |
| 2024-09-24 | 0 | $2.53M | TASK ORDER FOR SACRED OAKS SOLAR PROJECT SEE PROJECT DETAILS IN THE ATTACHMENT CONTRACTOR'S PROPOSAL. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗