75N99022F00001↗

Cutlass Contracting LLC received this contract from Nih a E Construction, National Institutes of Health: $350.7K obligated so far for construction of miscellaneous buildings. Its period of performance ended 2025-09-30.

Key facts · data as of Oct 26, 2026

Recipient
Cutlass Contracting LLC
Awarding agency
National Institutes of Health (Department of Health and Human Services)
Contracting office
Nih a E Construction (75N990)
Obligated to date
$350.7K
Potential value
$4.67M
Ends
2025-09-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.

Cite this page: SpendQuery, Award 75N99022F00001, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_75N99022F00001_7529_75N99019D00024_7529

C109753 BUILDING 31A 5TH FLOOR RENOVATION COR - DAVID SATTERLEE CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT

Delivery Order · National Institutes of Health · to Cutlass Contracting LLC (UEI MFMVJMYLMV17) · data as of 2026-10-26

Obligated to date$350.7K9 actions
Current value$4.67Mwith options exercised
Period2022-04-21 → 2025-09-30current end date

What it is

Product or service
Construction of Miscellaneous Buildings (PSC Y1JZ)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
Nih a E Construction (75N990)
Competition
Full and open competition · 3 offers received
Set-aside
SDVOSB
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 75N99019D00024
Where the work is
Montgomery, MD · district MD-08

Obligations by fiscal year

FY2023$258.2K
FY2024$21.1K
FY2025$71.4K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

9 actions since 2023-02-16. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-05-23P00010Supplemental agreement (work within scope)$71.4KC109753 MOD 10 TO INCORPORATE SUPPLEMENTAL REPLACEMENT ELEVATOR SIDING WORK ON THE 5TH FL OF BUILDING 31A AS OUTLINED IN THE CO7 SOW. COR - GARY ALDRED CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT
2025-03-05P00009Supplemental agreement (work within scope)$0C109753 MOD 09 TO EXTEND THE PERIOD OF PERFORMANCE AT NO COST TO THE GOVERNMENT. COR - GARY ALDRED CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT
2024-05-20P00008Supplemental agreement (work within scope)$0C109753 MOD 08 TO ADMINISTRATIVELY SWAP FUNDING RESULTING IN A NET ZERO CHANGE IN OBLIGATED FUNDING ON THE CONTRACT AND EXTEND THE PERIOD OF PERFORMANCE AT NO COST TO THE GOVERNMENT. COR - GARY ALDRED CO - DAN BURK CS - DAVE SEID VENDOR POC - HE
2023-12-04P00007Supplemental agreement (work within scope)$21.1KC109753 MOD 07 TO ADD FUNDING TO INCORPORATE SUPPLEMENTAL WORK OUTLINED IN THE CO6 SOW. COR - GARY ALDRED CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT
2023-08-14P00006Supplemental agreement (work within scope)$40.1KC109753 MOD 06 TO ADD FUNDING TO INCORPORATE SUPPLEMENTAL WORK OUTLINED IN THE CO5 SOW. COR - GARY ALDRED CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT
2023-05-08P00005Supplemental agreement (work within scope)$16.0KC109753 MOD 05 TO ADD FUNDING TO INCORPORATE SUPPLEMENTAL WORK OUTLINED IN THE CO4 SOW. COR - GARY ALDRED CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT
2023-04-18P00004Supplemental agreement (work within scope)$57.4KC109753 MOD 04 TO ADD FUNDING TO ADDRESS REQUEST FOR EQUITABLE ADJUSTMENT (REA) 01 OUTLINED IN THE PCO# 0005 PROPOSAL DATED 2/3/23 IN FULL AND TO EXTEND THE PERIOD OF PERFORMANCE AT NO COST TO THE GOVERNMENT THROUGH 9/18/2023. COR - GARY ALDRED CO
2023-04-06P00003Supplemental agreement (work within scope)$33.0KC109753 MOD 03 TO ADD SUPPLEMENTAL WORK WITHIN SCOPE AS OUTLINED IN THE CO#3 SOW FOR THE BUILDING 31A 5TH FLOOR RENOVATION COR - GARY ALDRED CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT
2023-02-16P00002Supplemental agreement (work within scope)$111.7KC109753 MOD 02 TO ADD SUPPLEMENTAL WORK WITHIN SCOPE AS OUTLINED IN THE CO#2 SOW FOR THE BUILDING 31A 5TH FLOOR RENOVATION COR - DAVID SATTERLEE CO - DAN BURK CS - DAVE SEID VENDOR POC - HEATH ABBOTT

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗