75N99022F00002↗
Hensel Phelps Construction Co received this contract from Nih a E Construction, National Institutes of Health: $87.94M obligated so far for construction of miscellaneous buildings. Its period of performance ended 2026-10-25.
Key facts · data as of Oct 25, 2026
- Recipient
- Hensel Phelps Construction Co
- Awarding agency
- National Institutes of Health (Department of Health and Human Services)
- Contracting office
- Nih a E Construction (75N990)
- Obligated to date
- $87.94M
- Potential value
- $195.72M
- Ends
- 2026-10-25
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award 75N99022F00002, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_75N99022F00002_7529_75N99019D00016_7529
Hensel Phelps Construction Co: all federal awards · Department of Health and Human Services: spending · Nih a E Construction: what it buys · The follow-on: recompete brief
C103754 - VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA
Up for re-bid: ends 2026-10-25. Recompete brief → · NIH MULTIPLE-AWARD CONSTRUCTION CONTRACT (MACC) FOR GENERAL CONSTRUCTION SERVICES ↗
What it is
- Product or service
- Construction of Miscellaneous Buildings (PSC Y1JZ)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Nih a E Construction (75N990)
- Competition
- Full and open competition · 3 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 75N99019D00016
- Where the work is
- Montgomery, MD · district MD-08
- Funding law
- COVID-19 laws
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
47 actions since 2022-10-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-30 | P00055 | Supplemental agreement (work within scope) | $800.1K | C103754: THE REASON FOR THIS MOD IS TO INCORPORATE VARIOUS DESIGN REVISIONS AND WORK TO COMPLETE THE CONSTRUCTION OF BLDG. 40A. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2026-09-17 | P00054 | Supplemental agreement (work within scope) | $111.5K | C103754: THE REASON FOR THIS MOD IS TO INCORPORATE THE DESIGN REVISIONS AND VARIOUS WORK TO COMPLETE THE CONSTRUCTION. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2026-09-03 | P00053 | Supplemental agreement (work within scope) | $1.57M | C103754: THE REASON FOR THIS MOD IS TO INCORPORATE THE OVERALL ADDS AND DEDUCTS AS A RESULT OF BIM COORDINATION AND VARIOUS WORK TO COMPLETE THE CONSTRUCTION. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2026-07-29 | P00052 | Supplemental agreement (work within scope) | $9.32M | C103754: THE REASON FOR THIS MOD IS TO INCORPORATE THE OVERALL ADDS AND DEDUCTS AS A RESULT OF BIM COORDINATION. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2026-07-16 | P00051 | Supplemental agreement (work within scope) | $0 | THE REASON FOR THIS MODIFICATION IS TO EXTEND THE CONSTRUCTION COMPLETION DATE TO PROVIDE ADDITIONAL TIME TO COMPLETE CONSTRUCTION. WITHOUT THIS CHANGE, THE PROJECT WILL NOT BE COMPLETE AND USABLE TO SUPPORT THE MISSION. |
| 2026-06-23 | P00050 | Supplemental agreement (work within scope) | $1.60M | C103754: THE REASON FOR THIS MOD IS TO INCORPORATE VARIOUS DESIGN REVISIONS AND WORK TO COMPLETE THE CONSTRUCTION OF BLDG. 40A. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2026-04-23 | P00049 | Supplemental agreement (work within scope) | $0 | C103754: THE REASON FOR THIS MODIFICATION IS TO EXTEND THE CONSTRUCTION COMPLETION DATE TO PROVIDE ADDITIONAL TIME TO COMPLETE CONSTRUCTION. WITHOUT THIS CHANGE, THE PROJECT WILL NOT BE COMPLETE AND USABLE TO SUPPORT THE MISSION. |
| 2026-04-16 | P00048 | Supplemental agreement (work within scope) | $1.31M | C103754: THE REASON FOR THIS MOD IS TO INCORPORATE VARIOUS DESIGN REVISIONS AND WORK TO COMPLETE THE CONSTRUCTION OF BLDG. 40A. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2026-03-11 | P00047 | Supplemental agreement (work within scope) | $516.2K | C103754: THE REASON FOR THIS MOD IS TO INCORPORATE VARIOUS DESIGN REVISIONS AND WORK TO COMPLETE THE CONSTRUCTION OF BLDG. 40A. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2026-01-30 | P00046 | Supplemental agreement (work within scope) | $405.3K | C103754 - THE REASON FOR THIS MOD IS TO INCORPORATE VARIOUS DESIGN REVISIONS AND WORK TO COMPLETE THE CONSTRUCTION OF BLDG. 40A. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2025-09-30 | P00045 | Supplemental agreement (work within scope) | $4.22M | C103754 - THE REASON FOR THIS MOD IS TO INCORPORATE VARIOUS DESIGN REVISIONS AND WORK TO COMPLETE THE CONSTRUCTION OF BLDG. 40A. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2025-09-27 | P00044 | Supplemental agreement (work within scope) | $1.84M | C103754 - THE REASON FOR THIS MOD IS TO PROVIDE FURNITURE FOR TURNKEY OF THE BUILDING 40A NORTH TOWER VRC LABORATORY EXPANSION PROJECT. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2025-09-18 | P00043 | Supplemental agreement (work within scope) | $17.95M | C103754 - THE REASON FOR THIS MOD IS TO INSTALL DEMOUNTABLE PARTITIONS AND LABORATORY EQUIPMENT TO PROVIDE A USABLE SPACE. WITHOUT IT, THE PROJECT CAN'T BE COMPLETED TO SUPPORT THE MISSION. |
| 2025-09-15 | P00042 | Change order | $3.49M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER. THE REASON FOR THIS MODIFICATION IS TO INCLUDE THE COST INCURRED BY TRADE PARTNERS FOR UNFORESEEN CONDITIONS AND DESIGN ERRORS THAT HAVE EXTENDED THE DURATION OF THE CONSTRUCTION OF THE BUILDING. |
| 2025-07-01 | P00041 | Supplemental agreement (work within scope) | $5.09M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER. THE REASON FOR THIS MODIFICATION IS TO COVER THE COST INCURRED BY TRADE PARTNERS FOR UNFORESEEN CONDITIONS AND DESIGN ERRORS THAT HAVE EXTENDED THE DURATION OF THE CONSTRUCTION OF THE BUILDING. |
| 2025-05-30 | P00040 | Supplemental agreement (work within scope) | $1.43M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER. THE REASON FOR THIS MODIFICATION IS TO PROVIDE BIM COORDINATION, DOAS UNIT PIPING AND MECHANICAL PLATFORM COORDINATION, DOOR SCHEDULE CLARIFICATIONS, FLOOD TESTING, AND DELINEATION OF BLDG.40/40A OF |
| 2025-04-17 | P00039 | Supplemental agreement (work within scope) | $5.51M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER. THE REASON FOR THIS MODIFICATION IS FOR A CONTRACT SCHEDULE EXTENSION THAT COVERS UNFORESEEN CONDITIONS AND DESIGN ERRORS THAT HAVE EXTENDED THE DURATION OF THE CONSTRUCTION OF THE BUILDING. |
| 2025-04-14 | P00038 | Supplemental agreement (work within scope) | $858.5K | THE REASON FOR THIS MODIFICATION IS TO PROVIDE BIM COORDINATION AND ADDITIONAL LABOR TO REMOVE DEBRIS AS WELL AS TO FURNISH AND INSTALL THE INTERSTITIAL FLOOR SURFACE AND NEW PUMP IMPELLERS IN THE CHILLED WATER PUMPS 4 AND 5. |
| 2024-12-20 | P00037 | Supplemental agreement (work within scope) | $464.0K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-11-27 | P00036 | Supplemental agreement (work within scope) | $652.1K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-09-28 | P00035 | Supplemental agreement (work within scope) | $1.95M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-09-03 | P00034 | Supplemental agreement (work within scope) | $1.72M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-07-16 | P00033 | Supplemental agreement (work within scope) | $1.44M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-06-14 | P00032 | Supplemental agreement (work within scope) | $382.0K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-05-03 | P00031 | Supplemental agreement (work within scope) | $487.1K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-04-03 | P00030 | Supplemental agreement (work within scope) | $898.4K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-03-14 | P00029 | Supplemental agreement (work within scope) | $125.5K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-03-12 | P00028 | Supplemental agreement (work within scope) | $6.70M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2024-01-31 | P00027 | Supplemental agreement (work within scope) | $1.94M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-12-21 | P00026 | Supplemental agreement (work within scope) | $277.9K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-11-28 | P00025 | Supplemental agreement (work within scope) | $431.3K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-10-30 | P00024 | Supplemental agreement (work within scope) | $44.7K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-09-22 | P00023 | Supplemental agreement (work within scope) | $406.6K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-09-12 | P00022 | Supplemental agreement (work within scope) | $110.6K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-08-06 | P00021 | Supplemental agreement (work within scope) | $120.8K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-07-18 | P00020 | Supplemental agreement (work within scope) | $83.3K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-07-05 | P00019 | Supplemental agreement (work within scope) | $10.66M | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-06-08 | P00018 | Supplemental agreement (work within scope) | $599.7K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-05-24 | P00017 | Administrative change | $0 | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-05-10 | P00016 | Supplemental agreement (work within scope) | $465.5K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2023-04-27 | P00015 | Supplemental agreement (work within scope) | $356.2K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2022-12-28 | P00014 | Supplemental agreement (work within scope) | $76.4K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2022-12-08 | P00013 | Supplemental agreement (work within scope) | $711.5K | VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2022-11-18 | P00012 | Change order | $225.2K | C103754 - VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2022-11-16 | P00011 | Change order | $433.0K | C103754 - VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2022-11-08 | P00010 | Change order | $56.9K | C103754 - VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
| 2022-10-31 | P00009 | Change order | $95.0K | C103754 - VRC LABORATORY EXPANSION, BUILDING 40A NORTH TOWER, BETHESDA |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗