Hensel Phelps Construction Co received this contract from Nih a E Construction, National Institutes of Health: $63.21M obligated so far for construction of miscellaneous buildings. It runs to 2029-01-25.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 75N99022F00003, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_75N99022F00003_7529_75N99019D00016_7529
Hensel Phelps Construction Co: all federal awards · Department of Health and Human Services: spending · Nih a E Construction: what it buys
C103157: SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
42 actions since 2022-11-10. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-24 | P00044 | Supplemental agreement (work within scope) | $552.7K | C103157 THIS MODIFICATION INCORPORATES NCI FURNITURE DESIGN AND PROCUREMENT TO MEET PHASE 2 COMPLETION DEADLINE. THERE IS NO CHANGE TO PERIOD OF PERFORMANCE. |
| 2026-09-24 | P00043 | Supplemental agreement (work within scope) | $168.1K | C103157 THIS MODIFICATION INCORPORATES ADDITIONAL WATER HEATER, VEHICLE GATE REPAIR, AND HEATER REPLACEMENT. THERE IS NO CHANGE TO PERIOD OF PERFORMANCE. |
| 2026-09-22 | P00042 | Supplemental agreement (work within scope) | $100.0K | C106418 THIS MODIFICATION INCORPORATES 2 SPARE BREAKERS FOR THE NEW CRC EMERGENCY SWITCHGEAR. |
| 2026-09-18 | P00041 | Supplemental agreement (work within scope) | $3.03M | C103157 THIS MODIFICATION INCORPORATES CFCI AIR COMPRESSOR, DOMESTIC MAIN WATER UPSIZING, LOCKSETS, PLUMBING FIXTURES, CARD READERS, MRI EMERGENCY COOLING, BSL3 SYSTEM SUPPLY, PH EQUALIZATION TANK AND TRANSFER PUMP, CLEAN ROOM ACCESS PANELS AND OTHER |
| 2026-09-18 | P00040 | Supplemental agreement (work within scope) | $485.0K | C103157 THIS MODIFICATION INCORPORATES ADD PH MONITORS, O2 YARD DESIGN, AN ADDITIONAL SUMP PUMP, B2 LEVEL RF SHIELDING, AND BIKE RACKS. THERE IS CHANGE TO PERIOD OF PERFORMANCE. |
| 2026-08-31 | P00039 | Supplemental agreement (work within scope) | $254.7K | C106418 THIS MODIFICATION PROVIDES ADDITIONAL TECHNICAL SUPPORT SERVICES FOR CX AND INCREASED DIESEL FUEL ALLOWANCE. |
| 2026-08-04 | P00038 | Supplemental agreement (work within scope) | $1.25M | C103157 THIS MOD INCORPORATES MULTIPLE CHANGE ORDERS FOR REINSTATE MEN'S RESTROOMS, ADDED CEILING SERVICE PANELS, HIGH PURITY WATER, ELEVATOR SUMP PUMP UPSIZING, MRI NON-FERROUS MATERIALS COORDINATION, AND IT RACK RECEPTACLE CHANGES. |
| 2026-06-30 | P00037 | Supplemental agreement (work within scope) | $3.65M | C106418 THIS MOD INCORPORATES MULTIPLE CHANGE ORDERS FOR EXISTING RETURN PUMP PIPING REPAIR, RFI0297R2 RESPONSE, NEW LOCKSET CORES, ADD OUTLETS, INVESTIGATE FEEDERS, CABLE PURCHASE ALLOWANCE, AND O&M SUPPORT SERVICES. |
| 2026-05-11 | P00036 | Supplemental agreement (work within scope) | $0 | C106418 THIS MOD INCORPORATES A 57 CALENDAR DAY NO COST TIME EXTENSION TO PHASES 0 AND 1 TO THE ESSEG PROJECT DUE TO UNFORESEEN CONDITIONS AND OUTAGE DELAYS. PHASE 0 AND 1 COMPLETION IS EXTENDED TO 30 APRIL 2026. |
| 2026-04-07 | P00035 | Supplemental agreement (work within scope) | $1.72M | C103157 THIS MOD INCORPORATES MULTIPLE CHANGES INCLUDING NON-ELECTRICAL VALIDATION ITEMS, HIGH PURITY WATER, SECURITY CAMERAS, STEAM VALVE REPLACEMENT, AND STERILIZER EQUIPMENT UPGRADES. WITHOUT THESE CHANGES THE BUILDING WILL BE UNOCCUPIABLE. |
| 2026-02-03 | P00034 | Supplemental agreement (work within scope) | $56.6K | C106418 THIS MOD INCORPORATES ELECTRICAL SYSTEM CHANGES DUE TO MULTIPLE RFI RESPONSES. WITHOUT THESE CHANGES THE BACKUP ELECTRICAL SYSTEM WOULD BE INCOMPLETE AND NON-COMPATIBLE WITH EXISTING SYSTEMS. |
| 2026-01-15 | P00033 | Supplemental agreement (work within scope) | $0 | C106418 THIS MOD INCORPORATES A 79 CALENDAR DAY NO COST TIME EXTENSION TO PHASES 0 AND 1 TO THE ESSEG PROJECT DUE TO UNFORESEEN CONDITIONS AND OUTAGE DELAYS. PHASE 0 AND 1 COMPLETION IS EXTENDED TO 4 MARCH 2026. |
| 2025-09-30 | P00032 | Supplemental agreement (work within scope) | $12.17M | C103157 THIS MOD INCORPORATES CUSTOMER REQUESTED DESIGN CHANGES TO CLINICAL AND HOSPITAL SPACES. WITHOUT THESE MODS THE SPACE WOULD BE INCOMPLETE RENDERING THE BUILDING UNOCCUPIABLE. |
| 2025-09-30 | P00031 | Supplemental agreement (work within scope) | $12.90M | C103157 THIS MOD INCORPORATES RF, MAGNETIC, AND EMI SHIELDING FOR MRI SPACES. WITHOUT THESE MODS THE SPACE WOULD BE INCOMPLETE RENDERING THE BUILDING UNOCCUPIABLE. |
| 2025-09-30 | P00030 | Supplemental agreement (work within scope) | $1.62M | C103157 THIS MOD IS UNILATERAL ACTION TO INCORPORATE CONSTRUCTION OF REVISED DESIGN MODIFICATIONS FOR LAB MODS, FLOOR FINISHES, AND REPURPOSE SPACES. WITHOUT THESE MODS THE SPACE WOULD BE INCOMPLETE RENDERING THE BUILDING UNOCCUPIABLE. |
| 2025-09-26 | P00029 | Funding only | $0 | C103157 THE PURPOSE OF THIS MODIFICATION IS PROVIDE CHANGES IN CONTRACT LINE ACCOUNTING DATA. |
| 2025-09-26 | P00028 | Supplemental agreement (work within scope) | $1.17M | C106418 THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE DESIGN BULLETINS AND RFI RESPONSES INTO CONSTRUCTION ACTIVITIES. WITHOUT THIS MODIFICATION THE GENERATORS WILL BE INCOMPLETE AND NON-USEABLE. |
| 2025-07-22 | P00027 | Supplemental agreement (work within scope) | $1.55M | THE REASON FOR THIS MODIFICATION IS TO INCLUDE VARIOUS CONSTRUCTION CHANGES DUE TO UNFORESEEN CONDITIONS, CUSTOMER REQUESTED CHANGES, AND DESIGN DEFICIENCIES. A NO COST TIME EXTENSION IS INCLUDED FOR WEATHER AND ADMIN. |
| 2025-05-22 | P00026 | Supplemental agreement (work within scope) | $178.4K | THE CONTRACT ACTION IS ESSENTIAL TO ENSURE CONSTRUCTION ACTIVITIES CONTINUE TO PROGRESS AND REMAIN COMPLIANT WITH ALL SAFETY, REGULATORY, AND FUNCTIONAL SPECIFICATIONS TO ENSURE THE FACILITY COMPLIES WITH THE HIGHEST INDUSTRY STANDARDS. |
| 2025-05-08 | P00025 | Supplemental agreement (work within scope) | $7.71M | THE CONTRACT ACTION IS ESSENTIAL TO ENSURE CONSTRUCTION ACTIVITIES CONTINUE TO PROGRESS AND REMAIN COMPLIANT WITH ALL SAFETY, REGULATORY, AND FUNCTIONAL SPECIFICATIONS TO ENSURE THE FACILITY COMPLIES WITH THE HIGHEST INDUSTRY STANDARDS. |
| 2025-03-31 | P00024 | Supplemental agreement (work within scope) | $311.1K | THIS CONTRACT ACTION IS ESSENTIAL TO ENSURE CONSTRUCTION ACTIVITIES CONTINUE TO PROGRESS AND REMAIN COMPLIANT WITH ALL SAFETY, REGULATORY, AND FUNCTIONAL SPECIFICATIONS TO ENSURE THE FACILITY COMPLIES WITH THE HIGHEST INDUSTRY STANDARDS. |
| 2025-01-07 | P00023 | Supplemental agreement (work within scope) | $263.0K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-11-01 | P00022 | Supplemental agreement (work within scope) | $304.1K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-09-27 | P00021 | Supplemental agreement (work within scope) | $292.4K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-09-26 | P00020 | Supplemental agreement (work within scope) | $2.84M | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-08-28 | P00019 | Supplemental agreement (work within scope) | $279.8K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-08-26 | P00018 | Supplemental agreement (work within scope) | $55.4K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-08-07 | P00017 | Supplemental agreement (work within scope) | $84.6K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-07-23 | P00016 | Supplemental agreement (work within scope) | $196.1K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-06-07 | P00015 | Supplemental agreement (work within scope) | $187.7K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-06-03 | P00014 | Supplemental agreement (work within scope) | $482.2K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-05-28 | P00013 | Supplemental agreement (work within scope) | $101.8K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-03-28 | P00012 | Supplemental agreement (work within scope) | $119.5K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-02-13 | P00011 | Supplemental agreement (work within scope) | $27.9K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2024-01-17 | P00010 | Supplemental agreement (work within scope) | $0 | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2023-12-05 | P00009 | Supplemental agreement (work within scope) | $202.4K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2023-10-26 | P00008 | Supplemental agreement (work within scope) | $28.9K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2023-09-19 | P00007 | Supplemental agreement (work within scope) | $1.59M | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2023-06-12 | P00006 | Administrative change | $0 | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2023-04-05 | P00005 | Supplemental agreement (work within scope) | $25.4K | SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION ELECTRICAL SWITCHING STATION AND EMERGENCY GENERATORS (ESSEG) |
| 2022-12-22 | P00004 | Supplemental agreement (work within scope) | $2.03M | C103157: SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION |
| 2022-11-10 | P00003 | Supplemental agreement (work within scope) | $5.21M | C103157: SURGERY, RADIOLOGY, AND LABORATORY MEDICINE (SRLM) BUILDING CONSTRUCTION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗