75N99026F00006↗

M. C. Dean, Inc. received this contract from Nih a E Construction, National Institutes of Health: $1.83M obligated so far for maintenance of other hospital buildings. It runs to 2027-04-03.

Key facts · data as of Oct 26, 2026

Recipient
M. C. Dean, Inc.
Awarding agency
National Institutes of Health (Department of Health and Human Services)
Contracting office
Nih a E Construction (75N990)
Obligated to date
$1.83M
Potential value
$1.83M
Ends
2027-04-03

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.

Cite this page: SpendQuery, Award 75N99026F00006, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_75N99026F00006_7529_75N99024A00002_7529

C202042 THIS PROJECT CONSISTS OF PROVIDING FULL DESIGN FOR THE REPLACEMENT OF THE FIRE ALARM HARDWARE IN BUILDING 10, MOVING FROM THE SIEMENS MXL FIRE ALARM CONTROL PANEL SYSTEM TO THE SIEMENS XLS FIRE ALARM CONTROL PANEL SYSTEM RODNEY KONO

Bpa Call · National Institutes of Health · to M. C. Dean, Inc. (UEI RD55NEXJ5EW4) · data as of 2026-10-26

Obligated to date$1.83M1 action
Current value$1.83Mwith options exercised
Period2026-09-30 → 2027-04-03current end date

Up for re-bid: ends 2027-04-03. Recompete brief →

What it is

Product or service
Maintenance of Other Hospital Buildings (PSC Z1DZ)
Industry
Engineering Services (NAICS 541330)
Contracting office
Nih a E Construction (75N990)
Competition
Full and open competition
Pricing
Firm fixed price
How it was bought
Blanket purchase agreement (BPA) · under 75N99024A00002
Where the work is
Montgomery, MD · district MD-08

Obligations by fiscal year

FY2026$1.83M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

1 action since 2026-09-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-300$1.83MC202042 THIS PROJECT CONSISTS OF PROVIDING FULL DESIGN FOR THE REPLACEMENT OF THE FIRE ALARM HARDWARE IN BUILDING 10, MOVING FROM THE SIEMENS MXL FIRE ALARM CONTROL PANEL SYSTEM TO THE SIEMENS XLS FIRE ALARM CONTROL PANEL SYSTEM RODNEY KONO

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗