80GRC025F7063↗
Pinnacle Construction Development Group, Inc. received this contract from Nasa Glenn Research Center, National Aeronautics and Space Administration: $9.49M obligated so far for construction of government-owned government-operated (gogo) r&d facilities. It runs to 2027-06-10.
Key facts · data as of Oct 23, 2026
- Recipient
- Pinnacle Construction Development Group, Inc.
- Awarding agency
- National Aeronautics and Space Administration
- Contracting office
- Nasa Glenn Research Center (80GRC0)
- Obligated to date
- $9.49M
- Potential value
- $9.49M
- Ends
- 2027-06-10
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 80GRC025F7063, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_80GRC025F7063_8000_80GRC020D0012_8000
Pinnacle Construction Development Group, Inc.: all federal awards · National Aeronautics and Space Administration: spending · Nasa Glenn Research Center: what it buys · The follow-on: recompete brief
PROJECT 33233 ATF CRYOGENIC FACILITY
Up for re-bid: ends 2027-06-10. Recompete brief → · Aerospace Power Systems Laboratory (APSL) Facility ↗
What it is
- Product or service
- Construction of Government-Owned Government-Operated (Gogo) R&D Facilities (PSC Y1HB)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Nasa Glenn Research Center (80GRC0)
- Competition
- Full and open after exclusion of sources · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 80GRC020D0012
- Where the work is
- Cuyahoga, OH · district OH-11
- Funding law
- Other emergency or disaster supplementals
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
3 subawards totaling $0 (0.0% of what was obligated), as Pinnacle Construction Development Group, Inc. reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Sierra Lobo Inc | $0 | 1 | OH | 2025-09-29 | 2025-09-29 |
| K2M Design, Inc | $0 | 1 | FL | 2025-09-29 | 2025-09-29 |
| The Osborn Engineering Co | $0 | 1 | OH | 2025-09-29 | 2025-09-29 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2025-09-29 | Sierra Lobo Inc | $0 | AE SERVICES |
| 2025-09-29 | K2M Design, Inc | $0 | AE SERVICES |
| 2025-09-29 | The Osborn Engineering Co | $0 | AE SERVICES |
Every action
3 actions since 2025-09-22. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-02 | P00002 | Supplemental agreement (work within scope) | $1.23M | ATF CRYO |
| 2026-03-09 | P00001 | Supplemental agreement (work within scope) | $379.4K | ATF CRYOGENIC FACILITY |
| 2025-09-22 | 0 | $7.88M | PROJECT 33233 ATF CRYOGENIC FACILITY |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗