80KSC019F0003↗

BRPH Architects Engineers Inc received this contract from Nasa Kennedy Space Center, National Aeronautics and Space Administration: $70.9K obligated so far for architect and engineering- general: other. Its period of performance ended 2025-11-21.

Key facts · data as of Oct 23, 2026

Recipient
BRPH Architects Engineers Inc
Awarding agency
National Aeronautics and Space Administration
Contracting office
Nasa Kennedy Space Center (80KSC0)
Obligated to date
$70.9K
Potential value
$2.46M
Ends
2025-11-21

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award 80KSC019F0003, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_80KSC019F0003_8000_NNK16CA03B_8000

ENGINEERING SERVICES DURING THE CONSTRUCTION UPGRADE OF THE LIQUID HYDROGEN II (LH2) SYSTEM

Delivery Order · National Aeronautics and Space Administration · to BRPH Architects Engineers Inc (UEI PFSXDMNJBKS8) · data as of 2026-10-23

Obligated to date$70.9K16 actions
Current value$2.46Mwith options exercised
Period2018-10-17 → 2025-11-21current end date

What it is

Product or service
Architect and Engineering- General: Other (PSC C219)
Industry
Engineering Services (NAICS 541330)
Contracting office
Nasa Kennedy Space Center (80KSC0)
Competition
Full and open competition · 1 offer received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under NNK16CA03B
Where the work is
Brevard, FL · district FL-08

Obligations by fiscal year

FY2023$54.0K
FY2024$0
FY2025$17.0K
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

16 actions since 2023-05-09. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-11-13P00021Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION (ESDC) OF UPGRADE LIQUID HYDROGEN (LH) 2 SYSTEM, LAUNCH COMPLEX (LC)-39B
2025-09-17P00020Supplemental agreement (work within scope)$17.0KENGINEERING SERVICES DURING CONSTRUCTION (ESDC) OF UPGRADE LIQUID HYDROGEN (LH) 2 SYSTEM, LAUNCH COMPLEX (LC)-39B PCN:98985
2025-03-14P00019Change order$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM AT LAUNCH COMPLEX-39B
2025-02-12P00018Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM AT LAUNCH COMPLEX-39B
2024-11-13P00017Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM AT LAUNCH COMPLEX-39B
2024-09-17P00016Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM AT LAUNCH COMPLEX -39B
2024-08-26P00015Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM LAUNCH CENTER-39B.
2024-07-11P00014Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION OF UPGRADE LIQUID HYDROGEN 2 SYSTEM, LAUNCH COMPLEX 39B - MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE BY AUGUST 31, 2024
2024-05-22P00013Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION OF UPGRADE LIQUID HYDROGEN 2 SYSTEM, LAUNCH COMPLEX 39B,
2024-04-30P00012Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM LAUNCH COMPLEX 39B.
2024-03-28P00011Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM AT LAUNCH COMPLEX -39B. ESDC UPGRADE LH2 SYSTEM LC-39B MOD 0011 EXTEND POP.
2024-02-15P00010Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION OF UPGRADE LIQUID HYDROGEN 2 SYSTEM, LAUNCH COMPLEX 39B. EXTEND PERIOD OF PERFORMANCE TO MARCH 29, 2024 AT NO ADDITIONAL COST.
2024-01-16P00009Supplemental agreement (work within scope)$0UPGRADE LIQUID HYDROGEN 2 SYSTEM, LAUNCH COMPLEX 39B
2023-12-20P00008Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM AT LAUNCH COMPLEX -39B. MOD 8: INCORPORATES TECHNICAL DIRECTIVE 08, EXTENDS END DATE TO 1/19/20243 AT NO ADDITIONAL COST.
2023-09-14P00007Supplemental agreement (work within scope)$0ENGINEERING SERVICES DURING CONSTRUCTION UPGRADE LIQUID HYDROGEN 2 SYSTEM AT LAUNCH COMPLEX -39B. INCORPORATES TECHNICAL DIRECTIVE 07, EXTENDS END DATE TO 12/29/2023 AT NO ADDITIONAL COST.
2023-05-09P00006Supplemental agreement (work within scope)$54.0KENGINEERING SERVICES DURING THE CONSTRUCTION UPGRADE OF THE LIQUID HYDROGEN II (LH2) SYSTEM. MOD 6: INCORPORATE TECHNICAL DIRECTIVE (TD)06. TASK ORDER IS INCREASED, AND PERIOD OF PERFORMANCE IS EXTENDED.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗