80KSC023FA129↗
Aleut Construction LLC received this contract from Nasa Kennedy Space Center, National Aeronautics and Space Administration: $756.5K obligated so far for repair or alteration of office buildings. Its period of performance ended 2024-08-15.
Key facts · data as of Nov 25, 2026
- Recipient
- Aleut Construction LLC
- Awarding agency
- National Aeronautics and Space Administration
- Contracting office
- Nasa Kennedy Space Center (80KSC0)
- Obligated to date
- $756.5K
- Potential value
- $756.5K
- Ends
- 2024-08-15
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 25, 2026.
Cite this page: SpendQuery, Award 80KSC023FA129, data as of Nov 25, 2026, https://spendquery.com/award?id=CONT_AWD_80KSC023FA129_8000_80KSC021DA005_8000
Aleut Construction LLC: all federal awards · National Aeronautics and Space Administration: spending · Nasa Kennedy Space Center: what it buys
REMOVE & REPLACE RAILROAD CROSSING
What it is
- Product or service
- Repair or Alteration of Office Buildings (PSC Z2AA)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Nasa Kennedy Space Center (80KSC0)
- Competition
- Full and open after exclusion of sources · 4 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 80KSC021DA005
- Where the work is
- Brevard, FL · district FL-08
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
8 actions since 2023-06-08. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-06-20 | P00007 | Supplemental agreement (work within scope) | $77.0K | REMOVE & REPLACE RAILROAD CROSSING. THIS MODIFICATION INCORPORATES TECHNICAL NARRATIVE 05 AND EXTENDS THE PERIOD OF PERFORMANCE TO 08/15/2024. |
| 2024-06-12 | P00006 | Supplemental agreement (work within scope) | $30.3K | REMOVE & REPLACE RAILROAD CROSSING. THIS MODIFICATION INCORPORATES REQUEST FOR EQUITABLE ADJUSTMENT 1 AND EXTENDS THE PERIOD OF PERFORMANCE TO 07/31/2024. |
| 2024-05-01 | P00005 | Administrative change | $0 | REMOVE & REPLACE RAILROAD CROSSING. THIS MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE TO 06/18/2024. |
| 2024-03-19 | P00004 | Supplemental agreement (work within scope) | $121.0K | REMOVE & REPLACE RAILROAD CROSSING. THIS MODIFICATION INCORPORATES TN-04 AND EXTENDS THE PERIOD OF PERFORMANCE TO 05/04/2024. |
| 2024-01-09 | P00003 | Administrative change | $0 | REMOVE & REPLACE RAILROAD CROSSING. THIS MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE TO 04/19/2024. |
| 2023-10-18 | P00002 | Supplemental agreement (work within scope) | $8.5K | REMOVE & REPLACE RAILROAD CROSSING INCORPORATE TRACKING NUMBER (TN) 03 CONTRACT COMPLETION DATE TO REMAIN 3/7/2024. |
| 2023-07-24 | P00001 | Supplemental agreement (work within scope) | $54.5K | REMOVE & REPLACE RAILROAD CROSSING INCORPORATE TRACKING NUMBERS (TN) 01 AND 02 AND EXTEND CONTRACT COMPLETION DATE TO 3/7/2023 IN ACCORDANCE TO NOTICE TO PROCEED (NTP). |
| 2023-06-08 | 0 | $465.3K | REMOVE & REPLACE RAILROAD CROSSING |