CENTAUR UPPER STAGE FOR SPACE LAUNCH SYSTEM (SLS) TO BE PROVIDED IN SUPPORT OF THE ARTEMIS PROGRAM TO MEET NASA SLS PERFORMANCE SPECIFICATIONS AND TECHNICAL REQUIREMENTS.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
5 actions since 2026-06-18. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-09 | P00004 | Funding only | $3.50M | CENTAUR UPPER STAGE FOR SPACE LAUNCH SYSTEM (SLS) TO BE PROVIDED IN SUPPORT OF THE ARTEMIS PROGRAM TO MEET NASA SLS PERFORMANCE SPECIFICATIONS AND TECHNICAL REQUIREMENTS. |
| 2026-08-13 | P00003 | Funding only | $30.00M | CENTAUR UPPER STAGE FOR SPACE LAUNCH SYSTEM (SLS) TO BE PROVIDED IN SUPPORT OF THE ARTEMIS PROGRAM TO MEET NASA SLS PERFORMANCE SPECIFICATIONS AND TECHNICAL REQUIREMENTS. |
| 2026-07-22 | P00002 | Administrative change | $0 | CENTAUR UPPER STAGE FOR SPACE LAUNCH SYSTEM (SLS) TO BE PROVIDED IN SUPPORT OF THE ARTEMIS PROGRAM TO MEET NASA SLS PERFORMANCE SPECIFICATIONS AND TECHNICAL REQUIREMENTS. |
| 2026-07-08 | P00001 | Supplemental agreement (work within scope) | $1.00M | CENTAUR UPPER STAGE FOR SPACE LAUNCH SYSTEM (SLS) TO BE PROVIDED IN SUPPORT OF THE ARTEMIS PROGRAM TO MEET NASA SLS PERFORMANCE SPECIFICATIONS AND TECHNICAL REQUIREMENTS. |
| 2026-06-18 | 0 | $25.00M | CENTAUR UPPER STAGE FOR SPACE LAUNCH SYSTEM (SLS) TO BE PROVIDED IN SUPPORT OF THE ARTEMIS PROGRAM TO MEET NASA SLS PERFORMANCE SPECIFICATIONS AND TECHNICAL REQUIREMENTS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗